GAMBAR PROGRES PENGERJAAN

RIWAYAT PENGERJAAN PAKET KEGIATAN

05 Nov 2018 03:57:15

...

Core drill beton pelebaran jalan

Progress Pengerjaan: 99 % Umar


03 Nov 2018 03:43:20

...

Finising pengecatan leuning jembatan

Umar


02 Nov 2018 08:27:46

...

Finishing pengecatan

Umar


01 Nov 2018 03:30:49

...

Pengecatan tembok keliling

Umar


31 Oct 2018 03:51:34

...

Finishing akhir pekerjaan

Umar


30 Oct 2018 05:13:04

...

Pengecatan pagar keliling

Umar


29 Oct 2018 06:03:04

...

Finising pagar keliling depan balai desa

Progress Pengerjaan: 98 % Umar


27 Oct 2018 04:28:23

...

Finising sayap jembatan sebelah timur selatan

Umar


26 Oct 2018 06:31:42

...

Finising saluran beton dan tembok keliling

Umar


25 Oct 2018 02:30:00

...

Finising leuning

Umar


24 Oct 2018 02:24:42

...

Finishing leuning jembatan

Umar


23 Oct 2018 07:26:19

...

Finising leuning

Umar


23 Oct 2018 03:50:12

...

Finishing begesting saluran dan leuning jembatan

Umar


22 Oct 2018 06:17:03

...

Pemasangan begisting saluran

Progress Pengerjaan: 94 % Umar


20 Oct 2018 04:22:54

...

Pemasangan begisting saluran

Umar


19 Oct 2018 07:00:45

...

Pasang begesting plat saluran air

Umar


19 Oct 2018 03:36:52

...

Persiapan begisting saluran

Umar


18 Oct 2018 03:49:04

...

Pemasangan relling jembatan dan sayap jembatan

Umar


17 Oct 2018 01:45:40

...

Pekerjaan leuning jembatan

Umar


16 Oct 2018 06:59:02

...

Pemasangan leuning jembatan

Umar


15 Oct 2018 14:03:59

...

Cor beton fs' 45 depan balai desa Karanggambas

Umar


15 Oct 2018 07:03:28

...

Pemeliharaan cor beton plat jembatan

Umar


15 Oct 2018 03:28:08

...

Urugan sayap jembatan

Umar


14 Oct 2018 16:22:45

...

Pengecoran plat jembatan

Umar


13 Oct 2018 03:14:35

...

Pembesian plat jmbatan

Umar


12 Oct 2018 06:51:32

...

Pembesian plat jembatan

Umar


12 Oct 2018 02:37:18

...

Pmbesian plat jembatan

Umar


11 Oct 2018 07:52:47

...

Siap utk pembesian plat jembatan.

Umar


11 Oct 2018 07:51:58

...

Siap utk pembesian plat jembatan

Umar


10 Oct 2018 07:51:48

...

Pengelasan sear conektor

Progress Pengerjaan: 86 % Umar


09 Oct 2018 04:24:10

...

Pasang begesting plat jembatan

Umar


09 Oct 2018 03:37:11

...

Pemasangan begisting plat jembatan

Umar


08 Oct 2018 03:54:09

...

Pemasangan baja iwf (diafragma)

Umar


06 Oct 2018 07:29:46

...

Penyetelan gelagar baja IWF

Umar


06 Oct 2018 03:10:20

...

Pemasangan gelagar untuk salauran dan pasangan batu sayap jembatan

Umar


05 Oct 2018 07:44:36

...

Pemasangan gelagar baja jembatan

Umar


05 Oct 2018 03:57:26

...

Pasang gelagar baja IWF

Umar


05 Oct 2018 03:56:45

...

Menyelesaikan pas. batu untuk saluran air

Umar


04 Oct 2018 03:52:08

...

Pemasangan gelagar jembatan dan timpunan pilihan belakang abutmen

Umar


03 Oct 2018 07:13:12

...

Persiapan pasang gelagar baja

Umar


03 Oct 2018 03:02:15

...

Pemasanangan gelagar baja jembatan

Umar


02 Oct 2018 07:29:05

...

Timbunan pilihan belakang abutment

Progress Pengerjaan: 84 % Umar


02 Oct 2018 04:08:08

...

Syarif Darmawan


02 Oct 2018 04:06:44

...

Syarif Darmawan


01 Oct 2018 04:36:36

...

Pasangan batu saluran air

Umar


30 Sep 2018 15:20:56

...

Cor abutmen atas sisi timur

Umar


30 Sep 2018 13:35:15

...

Pengecoran abutmen sebelah timur

Umar


29 Sep 2018 04:19:24

...

Cek kesiapan cor abutment atas sisi timur

Umar


29 Sep 2018 04:17:40

...

Penyelesaian talud sayap jembatan

Umar


29 Sep 2018 04:16:54

...

Penyelesaian cor lantai jembatan

Umar


28 Sep 2018 07:24:34

...

Timbunan pilihan / sirtu belakang abutment

Umar


28 Sep 2018 07:23:38

...

Pengadaan gelagar IWF

Umar


28 Sep 2018 07:13:55

...

Pemasangan begiating abutmen sebelah timur dan pemasangan sayap jembatan pasangan batu

Umar


28 Sep 2018 01:37:39

...

Pemasangan sayap jembatan dan lantai sungai

Umar


27 Sep 2018 03:47:21

...

Penyempurnaan begesting abutment sisi timur

Umar


27 Sep 2018 03:46:28

...

Melanjutkan pas. batu sayap jembatan

Progress Pengerjaan: 62 % Umar


25 Sep 2018 08:26:04

...

Umar


25 Sep 2018 08:23:32

...

Umar


25 Sep 2018 08:16:34

...

Penyelesaian begesting, pas. sayap jembatan dan lantai jembatan

Umar


22 Sep 2018 06:37:15

...

Pasangan lantai jembatan ...

Umar


19 Sep 2018 06:09:25

...

Melanjutkan pas. batu sayap sisi barat utara

Umar


19 Sep 2018 06:08:23

...

Bongkar begesting abutment sisi timur

Umar


17 Sep 2018 15:06:43

...

Pengecoran abutmen sebelah barat

Umar


17 Sep 2018 06:59:01

...

Persiapan pengecoran abutmen sebelah barat

Umar


15 Sep 2018 06:56:33

...

Begisting abutmen barat

Umar


14 Sep 2018 07:17:25

...

Cor beton fs 45 pelebaran jalan

Umar


13 Sep 2018 14:28:39

...

Pengecoran abutmen sebelah timur

Umar


13 Sep 2018 14:16:43

...

Cor lanjutan abutment sisi timur

Umar


12 Sep 2018 04:29:21

...

Begisting abutmen sebelah barat

Umar


10 Sep 2018 02:11:41

...

Masih menunggu jadwal pengecoran abutment.

Umar


08 Sep 2018 04:36:41

...

Pasang begesting abutment sisi barat

Umar


07 Sep 2018 08:29:10

...

Menunggu kepastian cor beton abutmen

Umar


06 Sep 2018 03:36:27

...

Pasangan batu / sayap jembatan

Progress Pengerjaan: 45 % Umar


04 Sep 2018 07:12:52

...

Kegiatan Begisting

Umar


01 Sep 2018 07:53:51

...

Buka begesting abutment sisi barat

Umar


01 Sep 2018 07:53:01

...

Begesting abutment sisi timur

Umar


31 Aug 2018 07:51:16

...

Umar


29 Aug 2018 02:07:39

...

Pekerjaan sayap jembatan

Umar


25 Aug 2018 04:16:08

...

Siap cor abutment sisi barat

Umar


25 Aug 2018 04:13:45

...

Pas. batu (sayap jembatan)

Umar


24 Aug 2018 08:34:42

...

Umar


23 Aug 2018 04:47:42

...

Begisting abutmen

Umar


21 Aug 2018 07:48:08

...

Umar


21 Aug 2018 07:47:28

...

Umar


20 Aug 2018 04:49:38

...

Umar


16 Aug 2018 18:25:15

...

Lanjut cor beton peil_cap abutment sisi timur.

Umar


16 Aug 2018 18:22:41

...

Cor peil_cap abutment sisi barat selesai.

Umar


16 Aug 2018 15:44:29

...

Lembur cor beton abutment.

Umar


16 Aug 2018 04:07:33

...

Umar


15 Aug 2018 04:29:23

...

Pembesian

Umar


14 Aug 2018 04:04:31

...

Umar


13 Aug 2018 07:01:53

...

Galian sayap jembatannn

Umar


12 Aug 2018 09:41:09

...

Umar


10 Aug 2018 06:58:16

...

Umar


10 Aug 2018 04:16:29

...

Melanjutkan pembesian abutment sisi barat.

Umar


10 Aug 2018 04:15:25

...

Melanjutkan pembesian abutment sisi barat.

Umar


09 Aug 2018 01:47:34

...

proses pembesian n pemasangan begisting abutment

Syarif Darmawan


09 Aug 2018 01:46:42

...

begisting abutment siap utk pengecoran

Syarif Darmawan


08 Aug 2018 07:24:53

...

Melanjutkan pembesian abutment sisi barat.

Umar


07 Aug 2018 06:37:37

...

Pengecoran box culvert

Umar


06 Aug 2018 06:05:16

...

Monitoring plt bupati purbalingga

Umar


04 Aug 2018 07:51:24

...

Melanjutkan pembesian dan pasang begesting poer abutment sisi timur.

Umar


03 Aug 2018 03:21:27

...

Pembesian abutmen

Umar


02 Aug 2018 06:10:27

...

Pembesian abutmen sisi timur

Progress Pengerjaan: 24 % Umar


02 Aug 2018 04:16:26

...

Pekerjaan pembesian abutmen

CV. CAHAYA MAS


28 Jul 2018 06:11:02

...

Galian tanah pelebaran jalan

Umar


28 Jul 2018 06:09:35

...

Umar


28 Jul 2018 06:08:51

...

Pembesian box culvert

Umar


27 Jul 2018 11:55:33

...

Pekerjaan Lantai kerja abutmen

Umar


27 Jul 2018 07:21:29

...

pengerjaan galian abutment..

Syarif Darmawan


23 Jul 2018 08:14:10

...

Progress Pengerjaan: 13 % Umar


21 Jul 2018 08:38:07

...

Progress Pengerjaan: 12 % Umar


19 Jul 2018 06:24:36

...

galian abutment

Syarif Darmawan


PEMBANGUNAN JEMBATAN KARANGGAMBAS

Kontraktor : CV. CAHAYA MAS
Jangka Waktu Selesai : 180 Hari
Mulai Pengerjaan : 15 May 2018
Selesai Pengerjaan : 10 Nov 2018
Deskripsi Progress : Opritan jembatan

Progress Pengerjaan

100 %