GAMBAR PROGRES PENGERJAAN

RIWAYAT PENGERJAAN PAKET KEGIATAN

25 Oct 2018 08:09:46

...

Wasis


25 Oct 2018 08:09:31

...

Wasis


17 Oct 2018 10:02:35

...

Mutual cek, proses serah trima pekerjaan pertama

Wasis


17 Oct 2018 10:01:21

...

Wasis


17 Oct 2018 10:01:01

...

Wasis


02 Oct 2018 04:12:07

...

Overlay HRS & coredrill selesai

Tri Pitoyo


12 Aug 2018 04:56:50

...

Hamparan hrs

Progress Pengerjaan: 99 % Wasis


10 Aug 2018 09:29:48

...

Hamparan hrs s/d pj.2.055m'

Wasis


07 Aug 2018 11:19:07

...

Wasis


06 Aug 2018 08:30:40

...

Galian saluran

Wasis


04 Aug 2018 05:49:56

...

Sal beton

Progress Pengerjaan: 20 % Wasis


02 Aug 2018 08:16:50

...

Pas.batu talud

Wasis


01 Aug 2018 08:26:55

...

cor beton saluran

Wasis


31 Jul 2018 07:29:16

...

Cor beton saluran

Wasis


30 Jul 2018 11:39:32

...

Bekisting cor saluran

Wasis


28 Jul 2018 04:26:55

...

Siar pas.batu

Wasis


28 Jul 2018 04:22:44

...

Pas.bt.talud

Progress Pengerjaan: 19 % Wasis


28 Jul 2018 04:21:47

...

Wasis


27 Jul 2018 07:01:44

...

Cor plat gorong2

Wasis


26 Jul 2018 06:34:25

...

Wasis


25 Jul 2018 04:53:07

...

Wasis


24 Jul 2018 09:22:28

...

Galian untuk gorong2 sta 3+950

Wasis


23 Jul 2018 06:34:52

...

Galian gorong2 sta 3+950 sementara mengejar pek.gorong2 untuk mempercepat terlaksananya pek.hamparan HRS

Progress Pengerjaan: 19 % Wasis


23 Jul 2018 05:37:45

...

Pekerjaan gorong gorong

Tri Pitoyo


19 Jul 2018 13:42:08

...

Galian gorong gorong

Progress Pengerjaan: 18 % Wasis


19 Jul 2018 04:15:26

...

Pekerjaan gorong-gorong

Tri Pitoyo


PEMELIHARAAN BERKALA JALAN PAGUTAN - BUMISARI (DAK)

Kontraktor : PT. GELANG SAKTI ABADI
Jangka Waktu Selesai : 150 Hari
Mulai Pengerjaan : 15 May 2018
Selesai Pengerjaan : 11 Oct 2018
Deskripsi Progress : PHO

Progress Pengerjaan

100 %