GAMBAR PROGRES PENGERJAAN

RIWAYAT PENGERJAAN PAKET KEGIATAN

29 Sep 2018 07:07:47

...

Progress Pengerjaan: 100 % Jeni


20 Sep 2018 15:35:22

...

Pekerjaan marka jalan

Jeni


19 Sep 2018 13:20:05

...

Coredrill

Jeni


16 Sep 2018 13:04:28

...

Pekerjaan tinggal marka jalan

Progress Pengerjaan: 87 % Jeni


10 Sep 2018 13:24:56

...

Jeni


10 Sep 2018 13:24:42

...

Jeni


10 Sep 2018 13:24:32

...

Jeni


10 Sep 2018 13:24:02

...

Jeni


10 Sep 2018 13:23:45

...

Jeni


10 Sep 2018 13:23:23

...

Jeni


10 Sep 2018 13:23:09

...

Jeni


08 Sep 2018 09:10:38

...

Opname paching

Jeni


06 Sep 2018 04:07:48

...

Proses pemindahan tiang listrik

Jeni


03 Sep 2018 03:50:51

...

Rapat evaluasi

Jeni


03 Sep 2018 03:42:36

...

Rencana: 5.058 realisasi 4.161

Progress Pengerjaan: 4 % Jeni


01 Sep 2018 10:39:58

...

Jeni


31 Aug 2018 11:40:21

...

Masih menunggu tiang listrik dipindah

Jeni


27 Aug 2018 06:20:56

...

Jeni


27 Aug 2018 06:20:36

...

Jeni


20 Aug 2018 09:55:15

...

Sampai saat ini belum ada kegiatan

Jeni


03 Aug 2018 10:27:02

...

Uitzet antara Penyedia Jasa, Staff Teknis PUPR, Konsultan Pengawas

Jeni


PENINGKATAN JALAN CAHYANA BARU (LANJUTAN)

Kontraktor : CV. ANJALLY CORP
Jangka Waktu Selesai : 120 Hari
Mulai Pengerjaan : 27 Jul 2018
Selesai Pengerjaan : 23 Nov 2018
Deskripsi Progress : Pemeriksaan PHO

Progress Pengerjaan

100 %