GAMBAR PROGRES PENGERJAAN

RIWAYAT PENGERJAAN PAKET KEGIATAN

06 Dec 2018 13:24:35

...

Lilik


04 Dec 2018 05:36:03

...

Lilik


03 Dec 2018 01:05:44

...

Pembesian lantai

Progress Pengerjaan: 90 % Lilik


26 Nov 2018 11:49:05

...

Lilik


24 Nov 2018 21:46:02

...

Begisting

Progress Pengerjaan: 88 % Lilik


23 Nov 2018 07:08:24

...

Begisting

Lilik


22 Nov 2018 09:53:47

...

Begisting

Lilik


21 Nov 2018 12:53:19

...

Begisting lantai jemb.

Lilik


19 Nov 2018 09:44:19

...

Bronjong & gelagar selesai

Lilik


19 Nov 2018 09:43:33

...

Bronjong

Lilik


17 Nov 2018 08:31:11

...

Bronjong

Progress Pengerjaan: 87 % Lilik


10 Nov 2018 15:20:29

...

Pemasangan gelagar

Progress Pengerjaan: 75 % Lilik


09 Nov 2018 06:27:36

...

Lilik


05 Nov 2018 08:47:40

...

Lilik


03 Nov 2018 08:41:33

...

Bronjong

Progress Pengerjaan: 60 % Lilik


02 Nov 2018 04:11:09

...

Bronjong

Lilik


01 Nov 2018 08:24:58

...

Pas. Bronjong

Lilik


31 Oct 2018 12:46:37

...

Galian utk bronjong

Lilik


30 Oct 2018 06:08:47

...

Urugan

Lilik


29 Oct 2018 08:32:33

...

Cor abutment

Progress Pengerjaan: 50 % Lilik


26 Oct 2018 09:55:48

...

Begisting abutment timur

Lilik


24 Oct 2018 09:46:57

...

Pembesian abutment timur

Lilik


22 Oct 2018 09:04:25

...

Cor abutment barat

Lilik


20 Oct 2018 10:42:25

...

Pembesian

Progress Pengerjaan: 46 % Lilik


18 Oct 2018 16:38:10

...

Lilik


17 Oct 2018 08:25:47

...

Lilik


16 Oct 2018 08:22:45

...

Lilik


15 Oct 2018 04:47:10

...

Begisting

Lilik


13 Oct 2018 07:14:21

...

Begisting abutment atas

Progress Pengerjaan: 43 % Lilik


12 Oct 2018 08:52:18

...

Pembesian

Lilik


10 Oct 2018 13:32:39

...

Pengecoran abutment timur

Lilik


09 Oct 2018 07:45:59

...

Begisting abutment timur

Lilik


08 Oct 2018 08:20:44

...

Pembesian abutment timur

Lilik


06 Oct 2018 07:31:02

...

Pembesian abutmen barat

Progress Pengerjaan: 33 % Lilik


05 Oct 2018 08:09:19

...

Cor abutment sisi timur

Lilik


05 Oct 2018 07:12:31

...

Cor abutment sisi timur

Lilik


04 Oct 2018 04:37:44

...

Pembesian abutment sisi timur

Progress Pengerjaan: 26 % Lilik


02 Oct 2018 04:10:01

...

pengecoran abutment sisi barat

Syarif Darmawan


01 Oct 2018 08:34:19

...

Lilik


29 Sep 2018 09:02:49

...

Begisting abutment atas

Lilik


28 Sep 2018 10:41:29

...

Begisting

Lilik


27 Sep 2018 06:26:12

...

Cor abutment

Lilik


26 Sep 2018 07:57:13

...

Pembesian

Lilik


25 Sep 2018 08:18:35

...

Begisting

Lilik


24 Sep 2018 04:37:38

...

Begisting abutment

Lilik


22 Sep 2018 05:59:43

...

Pembesian abudment

Progress Pengerjaan: 17 % Lilik


21 Sep 2018 13:03:36

...

Pembesian abudment

Lilik


20 Sep 2018 13:06:18

...

Cot abudment

Lilik


20 Sep 2018 07:52:53

...

Pembesian abudment

Lilik


08 Sep 2018 06:21:59

...

Cor bor pile

Progress Pengerjaan: 10 % Lilik


07 Sep 2018 11:42:06

...

Pembesian abudment

Lilik


05 Sep 2018 09:01:02

...

Bor pile sisi barat selesai

Lilik


04 Sep 2018 07:48:53

...

Bor pile

Lilik


01 Sep 2018 15:17:52

...

Bore pile

Lilik


28 Aug 2018 14:05:38

...

Bor sisi barat

Lilik


27 Aug 2018 13:40:17

...

Bor pile sebelah barat

Lilik


21 Aug 2018 04:36:12

...

Bor pile

Lilik


20 Aug 2018 09:31:29

...

Bor pile

Lilik


18 Aug 2018 05:45:49

...

Persiapan bor pile

Progress Pengerjaan: 3 % Lilik


15 Aug 2018 06:52:45

...

Bongkaran beton selesai, skr galian struktur

Lilik


11 Aug 2018 07:13:47

...

Bongkaran beton

Progress Pengerjaan: 1 % Lilik


09 Aug 2018 06:54:08

...

galian utk abutmen

Syarif Darmawan


09 Aug 2018 06:18:13

...

Bongkaran jemb lama

Lilik


04 Aug 2018 00:28:40

...

pekerjaan galian abutment

Syarif Darmawan


03 Aug 2018 03:51:24

...

Bongkaran abutmen lama

Lilik


PEMBANGUNAN JEMBATAN KALI CINGKRU RUAS JALAN GAMBARSARI KARANGTENGAH DI DESA MUNTANG

Kontraktor : CV. KARYA PUTRA WIJAYA
Jangka Waktu Selesai : 150 Hari
Mulai Pengerjaan : 23 Jul 2018
Selesai Pengerjaan : 19 Dec 2018
Deskripsi Progress :

Progress Pengerjaan

90 %