GAMBAR PROGRES PENGERJAAN

RIWAYAT PENGERJAAN PAKET KEGIATAN

21 Nov 2018 00:49:40

...

Fauzan


21 Nov 2018 00:49:27

...

Pekerjaan rigid

Progress Pengerjaan: 88 % Fauzan


07 Nov 2018 11:39:21

...

Fauzan


07 Nov 2018 11:39:07

...

Progress Pengerjaan: 79 % Fauzan


03 Nov 2018 05:47:37

...

Progress Pengerjaan: 71 % Fauzan


22 Oct 2018 06:01:16

...

Pengecoran rigid beton

Progress Pengerjaan: 66 % Fauzan


17 Oct 2018 04:30:15

...

Fauzan


17 Oct 2018 04:28:48

...

Pengecoran rigid beton

Progress Pengerjaan: 60 % Fauzan


02 Oct 2018 03:28:33

...

Fauzan


02 Oct 2018 03:28:21

...

Fauzan


02 Oct 2018 03:28:03

...

Pengecoran rigid beton

Progress Pengerjaan: 48 % Fauzan


24 Sep 2018 08:18:23

...

Fauzan


24 Sep 2018 08:17:35

...

Cuting perkerasan beton

Fauzan


24 Sep 2018 08:16:28

...

Pembesian Jembatan

Progress Pengerjaan: 38 % Fauzan


20 Sep 2018 06:01:19

...

Pengecoran rigid beton

Fauzan


20 Sep 2018 06:00:57

...

Test slum rigid beton

Fauzan


20 Sep 2018 06:00:23

...

Pengecoran rigid beton

Progress Pengerjaan: 31 % Fauzan


10 Sep 2018 02:40:01

...

Rigid beton sta 2+150

Progress Pengerjaan: 29 % Fauzan


04 Sep 2018 06:53:30

...

Rigid beton

Progress Pengerjaan: 24 % Fauzan


27 Aug 2018 03:58:05

...

Mohon dpercepat dlembur bok hujan kerjaan masih akeh

Widayanto


27 Aug 2018 03:52:53

...

Cor talud beton bertulang

Progress Pengerjaan: 22 % Fauzan


21 Aug 2018 01:02:38

...

Fauzan


21 Aug 2018 01:01:58

...

Pasangan talud dengan tulangan sta 2+800 kiri jalan

Progress Pengerjaan: 17 % Fauzan


13 Aug 2018 06:02:33

...

Pembesian kepala jembatan. Gua lawa

Progress Pengerjaan: 13 % Fauzan


08 Aug 2018 04:45:59

...

Pasang talud sta 4+350 kn jln

Fauzan


08 Aug 2018 04:43:00

...

Pasang pembesian jemb gua law

Fauzan


06 Aug 2018 09:13:21

...

Pas talud sta 2+250

Fauzan


06 Aug 2018 09:11:57

...

Penataan lahan sta 2+350

Fauzan


06 Aug 2018 09:08:35

...

Progress Pengerjaan: 8 % Fauzan


06 Aug 2018 02:48:32

...

Mohon dilembur yg lokasi cumbut dah milao udan

Widayanto


04 Aug 2018 09:47:42

...

Oke disirami dan ditutup geomembran

Widayanto


01 Aug 2018 08:39:59

...

Pas talud sta 4+400 kanan

Fauzan


01 Aug 2018 08:38:20

...

Cor beton fs 45 sta achir

Fauzan


30 Jul 2018 09:21:00

...

Pekerjaan pasangan talud

Fauzan


30 Jul 2018 09:19:54

...

Pekerjaan pasangan talud

Fauzan


30 Jul 2018 09:19:15

...

Pemerataan dan pemadatan lahan

Progress Pengerjaan: 6 % Fauzan


28 Jul 2018 10:31:02

...

Beton lc siwarak

Widayanto


28 Jul 2018 08:08:22

...

Penataan lahan

Fauzan


28 Jul 2018 08:07:07

...

Cor beton lc sta 5+400

Fauzan


27 Jul 2018 09:55:02

...

Cor beton lc /lante kerja sta 5+400. Barat Gualawa

Fauzan


27 Jul 2018 03:48:17

...

Penataan lahan sta 2+500 dan sta 4+350

Fauzan


27 Jul 2018 03:47:11

...

Pasangan talud sta 4+650 kiri

Fauzan


27 Jul 2018 03:22:35

...

Pasang talud sta 2+400 kiri

Fauzan


23 Jul 2018 03:30:03

...

Pasang talud sta..4+700 pasang abutmen sisi selatan sta achir/ gua lawa

Progress Pengerjaan: 2 % Fauzan


22 Jul 2018 00:00:01

...

Pas talud lokasi cumbut

Widayanto


19 Jul 2018 03:31:15

...

Pas batu talud

Widayanto


19 Jul 2018 02:34:27

...

Pekerjaan yang sedang dilaksanakan menggali abudment jembatan sisi selatan sta akhir (goa lawa), pekerjaan pemasangan talud sta 2+400 dan sta 4+650

Progress Pengerjaan: 2 % Fauzan


PENINGKATAN KAPASITAS JALAN TLAHAB LOR- SIWARAK (LANJUTAN ) (DAK)

Kontraktor : PT. IZA JAYA ABADI
Jangka Waktu Selesai : 180 Hari
Mulai Pengerjaan : 30 Jun 2018
Selesai Pengerjaan : 26 Dec 2018
Deskripsi Progress :

Progress Pengerjaan

88 %