GAMBAR PROGRES PENGERJAAN

RIWAYAT PENGERJAAN PAKET KEGIATAN

18 Oct 2018 16:35:53

...

Pho

Lilik


08 Oct 2018 04:21:25

...

Tmc

Lilik


21 Sep 2018 12:59:18

...

Progress Pengerjaan: 100 % Lilik


20 Sep 2018 07:53:53

...

Sal

Lilik


30 Aug 2018 07:13:04

...

Mulai hrs

Lilik


28 Aug 2018 14:07:23

...

Petcing

Lilik


27 Aug 2018 13:40:58

...

Patching

Lilik


14 Aug 2018 08:11:29

...

Didit Prayitno


14 Aug 2018 08:10:34

...

Saluran beton Sta. 0+950

Didit Prayitno


13 Aug 2018 07:16:22

...

Finishing sal

Lilik


11 Aug 2018 07:12:06

...

Sal beton sdh selesai

Progress Pengerjaan: 49 % Lilik


10 Aug 2018 10:00:11

...

Sal beton sta 1+109

Lilik


09 Aug 2018 08:11:02

...

Didit Prayitno


09 Aug 2018 08:10:20

...

Pembuatan saluran beton

Didit Prayitno


09 Aug 2018 06:16:11

...

Sal beton sta akhir ( 1+109 )

Lilik


08 Aug 2018 04:25:10

...

Sal beton sta 1+050

Lilik


04 Aug 2018 07:13:08

...

Sal beton smp sta 0+980

Progress Pengerjaan: 40 % Lilik


03 Aug 2018 10:01:57

...

Sal sta 0+950

Lilik


02 Aug 2018 10:35:49

...

Sal beton sta 0+900

Lilik


01 Aug 2018 10:18:37

...

Sal beton sta 0+860

Lilik


31 Jul 2018 07:51:02

...

Sal beton sta 0+830

Lilik


30 Jul 2018 14:00:14

...

Saluran beton

Didit Prayitno


30 Jul 2018 13:59:11

...

Pemasangan enlisting Sakiman beton

Didit Prayitno


30 Jul 2018 12:04:16

...

Sal. Beton sta 0+800

Lilik


30 Jul 2018 06:39:08

...

Sal beton sta0+800

Lilik


28 Jul 2018 10:36:35

...

Plesteran+aci gorong2 ; cor beton smp sta 0+760

Progress Pengerjaan: 32 % Lilik


27 Jul 2018 10:39:17

...

Plesteran; sal beton smp sta 720

Lilik


26 Jul 2018 10:02:55

...

Plesteran gorong2; saluran smp sta 690

Lilik


25 Jul 2018 07:50:54

...

Beton siklop

Lilik


24 Jul 2018 09:47:29

...

Sal. Beton smp sta 0+600; beton siklop sebelah gorong2 selesa

Lilik


23 Jul 2018 09:45:22

...

Galian sal smp sta 1+109; sal smp sta 0+600; pas batu gorong2 selesai

Lilik


21 Jul 2018 08:57:11

...

Pasangan batu gorong gorong

Progress Pengerjaan: 24 % CV. PRADITHA


21 Jul 2018 06:47:19

...

Galian saluran beton di sta akhir

Didit Prayitno


21 Jul 2018 06:45:17

...

Galian saluran beton

Didit Prayitno


21 Jul 2018 06:44:04

...

Pondasi plat beton

Didit Prayitno


21 Jul 2018 06:32:05

...

Pas. Batu gorong2 ; galian sal smp sta 0+900 ; beton sal

Progress Pengerjaan: 24 % Lilik


20 Jul 2018 11:55:49

...

Galian sal, beton cor, pas batu pd gorong2

Lilik


19 Jul 2018 22:08:43

...

Pekerjaan pembuatan gorong gorong sta 0+650

Progress Pengerjaan: 20 % CV. PRADITHA


19 Jul 2018 04:39:16

...

Galian sal & pas bt pada gorong2

Lilik


18 Jul 2018 12:30:19

...

Saluran smp sta 0+500

Lilik


18 Jul 2018 12:27:23

...

Saluran smp sta 0+500

Lilik


PEMELIHARAAN JALAN KARANG GAMBAS - MIPIRAN - SUSUKAN (BANYUMAS)

Kontraktor : CV. PRADHITA
Jangka Waktu Selesai : 120 Hari
Mulai Pengerjaan : 05 Jun 2018
Selesai Pengerjaan : 02 Oct 2018
Deskripsi Progress : Pphp

Progress Pengerjaan

100 %