GAMBAR PROGRES PENGERJAAN

RIWAYAT PENGERJAAN PAKET KEGIATAN

13 Sep 2018 09:04:30

...

Pemasangan Sandaran Railing

Progress Pengerjaan: 94 % Novi


12 Sep 2018 10:07:15

...

Patok pengaman jemb. K.kemusuk

Mahmud Hidayat


12 Sep 2018 10:06:01

...

Patok pengaman jemb

Mahmud Hidayat


12 Sep 2018 09:56:58

...

Mahmud Hidayat


12 Sep 2018 09:56:10

...

Latasir selesai

Mahmud Hidayat


12 Sep 2018 09:55:07

...

Pemasangan pipa sandaran

Mahmud Hidayat


07 Sep 2018 08:27:28

...

Pekerjaan Latasir Jembatan

Novi


06 Sep 2018 08:07:21

...

Pembangunan Talud

Novi


05 Sep 2018 04:03:36

...

Pekerjaan Lapen

Novi


04 Sep 2018 01:35:41

...

Pekerjaan Latasir

Progress Pengerjaan: 86 % Novi


31 Aug 2018 02:26:12

...

Cor tgl. 28 agara 2018

Mahmud Hidayat


31 Aug 2018 01:58:45

...

Pek.jemb. k. Kemusuk

Mahmud Hidayat


31 Aug 2018 01:57:34

...

Mahmud Hidayat


30 Aug 2018 02:35:48

...

Pembangunan Leuning

Novi


21 Aug 2018 07:27:04

...

Pembekistingan Plat Jembatan

Novi


20 Aug 2018 07:36:43

...

Pekerjaan Timbunan

Progress Pengerjaan: 50 % Novi


18 Aug 2018 09:01:25

...

Pemasangan Gelagar Jembatan

Novi


16 Aug 2018 04:23:56

...

Persiapan Pengecoran Balok Landas Sisi Selatan

Novi


15 Aug 2018 09:04:08

...

Pembesian Balok Landas dan Pembuatan Sayap Jembatan

Novi


11 Aug 2018 06:35:24

...

Penghamparan LPA STA 0+090

Progress Pengerjaan: 32 % Novi


10 Aug 2018 09:06:46

...

Penghamparan LPA

Novi


08 Aug 2018 05:13:13

...

Pembangunan Abutmen Sisi kiri

Novi


06 Aug 2018 09:52:53

...

Penghamparan LPA

Novi


04 Aug 2018 08:06:51

...

Pembangunan Abutmen dan pengecoran selimut beton abutmen

Progress Pengerjaan: 26 % Novi


03 Aug 2018 07:35:59

...

Pembangunan Abutmen ( selatan ) dan Pembangunan sayap jembatan ( utara )

Novi


02 Aug 2018 07:05:49

...

Pemasangan Bekisting untuk pengecoran selimut abutmen sisi utara

Novi


01 Aug 2018 07:22:32

...

Pembangunan Abutmen Jembatan

Novi


31 Jul 2018 04:47:42

...

Galian Abutmen dan Pembangunan Abutmen

Novi


30 Jul 2018 06:59:07

...

Pasangan Abutmen Jembatan

Novi


28 Jul 2018 11:40:57

...

Pembesian Selimut Abutmen dan Pembangunan Abutmen

Progress Pengerjaan: 17 % Novi


28 Jul 2018 06:14:40

...

Pembangunan abutmen dan pembesian selimut abutmen

Novi


27 Jul 2018 05:59:19

...

Pembuatan Abutmen dan galian abutmen

Novi


26 Jul 2018 07:48:44

...

Pas. Batu abutmen jembatan

Mahmud Hidayat


26 Jul 2018 07:47:09

...

Penggalian Abutmen dan pemasangan Abudmen

Novi


25 Jul 2018 08:20:33

...

Pek. Galian Abutmen dan pengecoran plat abutmen

Novi


25 Jul 2018 04:19:26

...

Galian Abutmen, dan pembesian lantai abutmen

Novi


23 Jul 2018 08:52:23

...

Pekerjaan Talud STA 0+250

Progress Pengerjaan: 14 % Novi


23 Jul 2018 03:02:35

...

Pek. Talud

Novi


23 Jul 2018 03:01:46

...

Pek. Talud samping jembatan

Novi


23 Jul 2018 03:00:31

...

Galian berbatu abutmen

Novi


21 Jul 2018 04:58:04

...

Galian abutmen jembatan..kondisi tanah batuan keras , harusnya pake bracker..

Mahmud Hidayat


18 Jul 2018 06:59:29

...

Keg. Galian Berbatu Abutmen

Novi


18 Jul 2018 06:24:53

...

Keg. Galian berbatu, Abutmen

Novi


PEMBANGUNAN JALAN PATEMON-GALUH-WIRASANA

Kontraktor : CV. INDESCO DEVELOPER
Jangka Waktu Selesai : 120 Hari
Mulai Pengerjaan : 25 May 2018
Selesai Pengerjaan : 21 Sep 2018
Deskripsi Progress : Pemeriksaan PHO

Progress Pengerjaan

100 %