GAMBAR PROGRES PENGERJAAN

RIWAYAT PENGERJAAN PAKET KEGIATAN

05 Sep 2018 09:10:15

...

Coredrill

Progress Pengerjaan: 100 % Andi


04 Sep 2018 08:37:06

...

HRS 04-09-2018

Andi


30 Aug 2018 12:42:31

...

Pekerjaan latasir selesai

Andi


28 Aug 2018 14:31:33

...

Pekerjaan latasir

Andi


13 Aug 2018 05:55:38

...

Galian perkerasan beton semen

Progress Pengerjaan: 67 % Andi


03 Aug 2018 04:34:17

...

Awal saluran beton bertulang

Andi


01 Aug 2018 02:39:30

...

Grill Penutup Saluran

Progress Pengerjaan: 58 % Andi


31 Jul 2018 04:52:59

...

Pek. Grill Penutup Saluran

Andi


30 Jul 2018 03:32:53

...

Pek. Plat penutup saluran

Andi


28 Jul 2018 02:57:38

...

Galian box culvert

Andi


26 Jul 2018 09:56:41

...

Galian Box Culvert

Andi


23 Jul 2018 05:35:54

...

Galian untuk pekerjaan gorong-gorong

Tri Pitoyo


22 Jul 2018 12:44:21

...

Saluran beton bertulang

Progress Pengerjaan: 45 % Andi


19 Jul 2018 07:00:46

...

Pekerjaan saluran beton

Tri Pitoyo


19 Jul 2018 05:19:27

...

Pekerjaan saluran beton bertulang

Progress Pengerjaan: 44 % Andi


18 Jul 2018 06:54:44

...

Papan Nama Proyek

Andi


PENINGKATAN JALAN BOJONGSARI - KAJONGAN / GIRI CENDANA

Kontraktor : CV. ZEIN PERWIRA MANDIRI
Jangka Waktu Selesai : 120 Hari
Mulai Pengerjaan : 18 May 2018
Selesai Pengerjaan : 14 Sep 2018
Deskripsi Progress : Pekerjaan HRS & coredrill sdh selesai

Progress Pengerjaan

100 %