GAMBAR PROGRES PENGERJAAN

RIWAYAT PENGERJAAN PAKET KEGIATAN

10 Sep 2018 23:56:14

...

Progress Pengerjaan: 89 % PT. AGUNG DARMA INTRA


05 Sep 2018 06:05:23

...

LC sebelah pasar hewan

PT. AGUNG DARMA INTRA


03 Sep 2018 02:26:34

...

galian sta 0+300 kiri pasar hewan

Progress Pengerjaan: 79 % PT. AGUNG DARMA INTRA


30 Aug 2018 05:25:45

...

cor lc sta 0+600 kiri

Progress Pengerjaan: 75 % PT. AGUNG DARMA INTRA


29 Aug 2018 07:24:26

...

Galian

Fauzan


27 Aug 2018 07:39:08

...

Urugan sisi pas. Talud.

Fauzan


21 Aug 2018 13:17:16

...

fs45 depan pasar layer ke 2

Progress Pengerjaan: 69 % PT. AGUNG DARMA INTRA


20 Aug 2018 14:17:38

...

Didit Prayitno


20 Aug 2018 14:16:56

...

Beton fs 45 sebelah terminal sisi kanan

Didit Prayitno


15 Aug 2018 08:02:35

...

Tim TP4D

Fauzan


15 Aug 2018 05:39:38

...

LC di dekat pasar hewan

Progress Pengerjaan: 65 % PT. AGUNG DARMA INTRA


14 Aug 2018 08:13:59

...

Didit Prayitno


14 Aug 2018 08:13:11

...

Ngwcor fs sebelah terminal

Didit Prayitno


13 Aug 2018 06:10:46

...

Selimut anti panas...

Fauzan


09 Aug 2018 07:50:00

...

Galian untuk persiapan LC

Didit Prayitno


09 Aug 2018 07:48:16

...

Beton cemen pelebaran depan bale deda babakan

Didit Prayitno


09 Aug 2018 06:35:49

...

Galian dpn sarwan

Fauzan


08 Aug 2018 05:29:19

...

lc depan polres

PT. AGUNG DARMA INTRA


07 Aug 2018 05:24:56

...

Pipa isi kabel lampu sorot tugu sudirman.

Fauzan


06 Aug 2018 07:36:47

...

cor fs45 di sta 1+150

Progress Pengerjaan: 57 % PT. AGUNG DARMA INTRA


03 Aug 2018 04:38:37

...

Fauzan


01 Aug 2018 04:19:01

...

Finishing

Fauzan


31 Jul 2018 13:18:23

...

cor fs45 pelebaran sta 0+650

PT. AGUNG DARMA INTRA


31 Jul 2018 10:32:34

...

Fauzan


31 Jul 2018 03:50:28

...

Kabel Listrik...

Fauzan


31 Jul 2018 02:46:18

...

Galian sta 0

Fauzan


30 Jul 2018 13:47:27

...

Didit Prayitno


30 Jul 2018 13:46:31

...

Pelebaran begin cemen

Didit Prayitno


30 Jul 2018 09:10:43

...

Tamu dr PT. Telkom pbg

Fauzan


30 Jul 2018 09:07:54

...

Galian babakan

Fauzan


30 Jul 2018 04:09:54

...

cor fs45 di sta 0+345

Progress Pengerjaan: 51 % PT. AGUNG DARMA INTRA


28 Jul 2018 12:50:30

...

Pengecoran beton pelebaran jalan

Fauzan


28 Jul 2018 12:05:03

...

Pengecoran beton pelebaran jalan

Fauzan


28 Jul 2018 05:13:25

...

Pembesian.

Fauzan


28 Jul 2018 05:12:45

...

Bekusting Plat besi.

Fauzan


28 Jul 2018 05:12:12

...

Air Curring Compond.

Fauzan


28 Jul 2018 04:47:21

...

Cor... Lantai kerja.

Fauzan


28 Jul 2018 04:29:05

...

Tim Monev DPU PR

Fauzan


28 Jul 2018 04:21:45

...

Kunjungan Tim Monev pk. Sukirman cs.

Fauzan


27 Jul 2018 03:48:48

...

Calon pas batu. Hasil galian utk urugan bahu jln.

Fauzan


26 Jul 2018 14:54:34

...

Lantai kerja depan nirmala

Didit Prayitno


25 Jul 2018 07:44:11

...

Pekerjaan lantai kerja perkerasan beton pelebaran jalan

Progress Pengerjaan: 51 % Fauzan


24 Jul 2018 06:12:39

...

Fauzan


23 Jul 2018 01:36:56

...

hari inu rencana cor fc10 sebelum perempatan Babakan

Progress Pengerjaan: 50 % PT. AGUNG DARMA INTRA


20 Jul 2018 04:15:42

...

Galian beton warung dpn rs nirmala

Fauzan


19 Jul 2018 04:15:27

...

Progress Pengerjaan: 50 % PT. AGUNG DARMA INTRA


19 Jul 2018 03:36:53

...

Galian tanah pelebaran kalan

Didit Prayitno


19 Jul 2018 03:30:35

...

Pekerjaan galian pelebaran jalan

Progress Pengerjaan: 50 % Fauzan


PENINGKATAN KAPASITAS JALAN LETNAN YUSUF (LANJUTAN) (DAK)

Kontraktor : PT. AGUNG DARMA INTRA
Jangka Waktu Selesai : 150 Hari
Mulai Pengerjaan : 26 Apr 2018
Selesai Pengerjaan : 22 Sep 2018
Deskripsi Progress : marka jalan

Progress Pengerjaan

100 %