GAMBAR PROGRES PENGERJAAN

RIWAYAT PENGERJAAN PAKET KEGIATAN

02 Oct 2018 03:41:20

...

Rapat evaluasi di kantor DPU-PR

Doni


28 Sep 2018 01:48:39

...

Pengujian beam fs

Progress Pengerjaan: 99 % Doni


14 Sep 2018 06:05:11

...

Pengukuran hasil pekerjaan

Doni


12 Sep 2018 09:52:37

...

Hrs. Selesai

Mahmud Hidayat


12 Sep 2018 09:51:21

...

Mahmud Hidayat


11 Sep 2018 14:08:43

...

Hamparan campuran aspal panas

Doni


11 Sep 2018 03:11:37

...

Pekerjaan pemadatan Campuran Aspal Panas

Doni


11 Sep 2018 03:11:12

...

Pekerjaan hamparan Campuran Aspal Panas

Doni


10 Sep 2018 06:43:00

...

Pekerjaan patching

Doni


08 Sep 2018 05:29:11

...

Pengukuran pekerjaan patching

Doni


03 Sep 2018 04:19:04

...

Rapat evaluasi di kantor DPU-PR seksi Bina Marga

Doni


02 Sep 2018 03:16:03

...

Pekerjaan patching

Progress Pengerjaan: 65 % Doni


01 Sep 2018 02:56:23

...

Pekerjaan patching segmen 1

Doni


30 Aug 2018 11:10:26

...

Core drill

Doni


30 Aug 2018 11:08:49

...

Core drill

Doni


28 Aug 2018 03:17:33

...

Core drill beton untuk pengecekan kedalaman

Doni


27 Aug 2018 05:28:09

...

Persiapan pengujian benda uji beton FS

Doni


21 Aug 2018 06:57:18

...

Pemotongan segmen beton

Doni


21 Aug 2018 06:56:48

...

Pengecekan ukuran segmen 1

Doni


20 Aug 2018 06:10:51

...

Proges minggu ke 14 tanggal 19 agustus 2018

Progress Pengerjaan: 64 % PT. SELABAYA INDAH PRATAMA


18 Aug 2018 04:18:06

...

STA 0+000 Puspawresti CS

Progress Pengerjaan: 64 % Doni


15 Aug 2018 05:00:21

...

Pemeliharaan beton STA 0+000

Doni


13 Aug 2018 12:30:14

...

Pemotongan segmen beton

Doni


13 Aug 2018 12:14:57

...

Pekerjaan beton FS segmen 1 STA 0+150 kiri

Doni


13 Aug 2018 06:18:22

...

Pengecekan oleh tim monitoring DPU-PR Kab. Purbalingga

Doni


13 Aug 2018 05:15:56

...

Pengecekan pelebaran jalan segmen 2

Doni


11 Aug 2018 09:38:33

...

Cor FS 45 STA 0+200

Progress Pengerjaan: 60 % Doni


10 Aug 2018 10:07:48

...

Pemeliharaan awal dengan curing compon

Doni


10 Aug 2018 08:04:55

...

Pengecoran Fs'45 segmen 1 STA 0+350 KIRI

Doni


09 Aug 2018 06:38:38

...

Rapat kordinasi di Kabupaten Purbalingga

Doni


07 Aug 2018 07:33:59

...

Perapian galian tanah dan pemasangan bekisting segmen 1 STA 0+200

Doni


06 Aug 2018 07:36:39

...

Pemeliharaan meggunakan curing compon segmen 1

Doni


06 Aug 2018 06:36:11

...

Penkerjaan pelebaran beton segmen 2. STA 0+150 an

Doni


04 Aug 2018 05:07:41

...

Perapian lahan dan pemasangan bekisting segmen utama

Progress Pengerjaan: 46 % Doni


03 Aug 2018 10:55:07

...

Pengecoran beton FS segmen 1

Doni


03 Aug 2018 07:50:43

...

Lantai kerja STA 0+450

Doni


02 Aug 2018 11:31:30

...

Pemeliharaan beton dengan membran penutup

Doni


02 Aug 2018 11:30:34

...

Pengecoran beton fs segmen 0+550

Doni


02 Aug 2018 11:30:08

...

Pemeliharaan curing compon

Doni


02 Aug 2018 09:52:59

...

Pemeliharaan curing compon pada beton

Doni


02 Aug 2018 09:52:23

...

Pengecoran fs STA 0+650

Doni


02 Aug 2018 04:54:57

...

Uji tarik besi di lab unsoed

Doni


02 Aug 2018 04:54:08

...

Uji tarik beton FS di lab unsoed

Doni


02 Aug 2018 04:53:30

...

Uji tekan beton FS di lab Unsoed

Doni


01 Aug 2018 05:33:18

...

Rapat evaluasi di kantor Bina Marga DPU-PR

Doni


30 Jul 2018 05:29:28

...

Pekerjaan beton lantai kerja segmen 2. Sta 0+300

Doni


28 Jul 2018 08:34:14

...

Pekerjaan Lantai Kerja STA 0+150 SEGMEN 2

Progress Pengerjaan: 33 % Doni


27 Jul 2018 10:56:38

...

Pekerjaan betom FS STA 0+900 KANAN

Doni


27 Jul 2018 10:23:02

...

Pekerjaan beton fs'45 segmen 2 STA 0+000 KANAN

Doni


27 Jul 2018 10:22:13

...

Perapian hasil galian

Doni


27 Jul 2018 10:21:29

...

Pengecekan ketebalan lantai kerja

Doni


27 Jul 2018 04:25:28

...

LC STA 0+825

Doni


26 Jul 2018 07:20:08

...

Pengecoran beton FS STA 1+025

Doni


26 Jul 2018 07:19:25

...

Pengecekan stik pemandu tebal beton 25cm

Doni


26 Jul 2018 07:12:45

...

Mahmud Hidayat


26 Jul 2018 07:12:15

...

Cor fs 45 sta 1+000

Mahmud Hidayat


26 Jul 2018 05:07:07

...

Galian tanah segmen 2. STA 0+250

Doni


25 Jul 2018 05:33:04

...

Pekerjaan Galian tanah Segmen 2

Doni


24 Jul 2018 07:22:34

...

Pengecoran beton fs'45

Doni


23 Jul 2018 08:57:21

...

Pekerjaan pelebaran beton FS'45 STA 1+200

Doni


21 Jul 2018 08:42:34

...

Pengecoran beton fs'45 STA 1+300an

Progress Pengerjaan: 22 % Doni


21 Jul 2018 07:18:01

...

Pekerjaan LC STA 1+100

Doni


21 Jul 2018 04:55:06

...

Mahmud Hidayat


21 Jul 2018 04:54:26

...

Lc pada sta 1+200an

Mahmud Hidayat


20 Jul 2018 16:57:24

...

Pekerjaan beton fs 45. STA 1+450 sebelah kanan

Doni


19 Jul 2018 19:59:00

...

Pengecoran fs 45. Sta 0+570

Doni


19 Jul 2018 05:22:23

...

Jl puspawresti bbsari 17,36 %

Mahmud Hidayat


19 Jul 2018 05:18:18

...

Cor beton fs' 45 STA 0+700an

Progress Pengerjaan: 17 % Doni


PENINGKATAN KAPASITAS JALAN PUSPAWRESTI CS KEC. BOBOTSARI (DAK)

Kontraktor : PT. SELABAYA INDAH PRATAMA
Jangka Waktu Selesai : 150 Hari
Mulai Pengerjaan : 18 May 2018
Selesai Pengerjaan : 14 Oct 2018
Deskripsi Progress : Pemeriksaan tmc

Progress Pengerjaan

100 %