GAMBAR PROGRES PENGERJAAN

RIWAYAT PENGERJAAN PAKET KEGIATAN

07 Sep 2018 03:27:13

...

Coredrill beton

Jeni


03 Sep 2018 03:44:55

...

Rapat Evaluasi

Progress Pengerjaan: 100 % Jeni


29 Aug 2018 03:50:35

...

Timbunan bahu.

Jeni


24 Aug 2018 09:09:59

...

PT. CAHAYA UTAMA SENTOSA


24 Aug 2018 08:00:13

...

Leveling badan jalan.

Jeni


20 Aug 2018 05:52:39

...

Pemeriksaan Termijn

Jeni


18 Aug 2018 05:20:51

...

Penutupan dilatasi dgn aspal

Progress Pengerjaan: 98 % Jeni


13 Aug 2018 02:55:26

...

Opname pelebaran.

Jeni


11 Aug 2018 09:11:09

...

Pasangan Leuning Gorong2

Jeni


10 Aug 2018 09:56:31

...

Pas. Batu talud Sta 2+350

Jeni


09 Aug 2018 08:13:54

...

Galian pas. Batu talud sta 2+350

Jeni


08 Aug 2018 03:48:58

...

Core drill beton

Jeni


06 Aug 2018 07:58:49

...

Test tarik besi tulangan

Progress Pengerjaan: 96 % Jeni


05 Aug 2018 04:05:33

...

Beton Fs 45 sta 2+350

Jeni


04 Aug 2018 07:36:32

...

Lantai kerja sta 2+400

Jeni


04 Aug 2018 06:50:19

...

Perapian hasil galian dan persiapan LC STA 2+400 (R)

Jeni


03 Aug 2018 09:03:18

...

Penyiapan badan jalan, sta 2+250

Jeni


02 Aug 2018 04:18:35

...

Pekerjaan plesteran ban bananan saluran Sta 1+250

Jeni


01 Aug 2018 21:13:10

...

Beton fs 45 sta 2+250 (R)

Jeni


01 Aug 2018 18:57:30

...

Beton fs 45 sta 2+250 (R)

Jeni


01 Aug 2018 15:03:59

...

Fs45 sta 2+130 an

Jeni


01 Aug 2018 05:34:02

...

Rapat evaluasi di DPU-PR

Jeni


31 Jul 2018 08:14:02

...

Plesteran & Siaran 1+200

Jeni


30 Jul 2018 20:27:29

...

Beton FS 45 sta 2+050 (R)

Jeni


30 Jul 2018 18:29:00

...

Curing compound

Jeni


30 Jul 2018 18:27:24

...

Curing compond

PT. CAHAYA UTAMA SENTOSA


30 Jul 2018 18:05:43

...

Vibrator beton...

PT. CAHAYA UTAMA SENTOSA


30 Jul 2018 16:24:22

...

Cek ketebalan beton sta 1+975

Progress Pengerjaan: 83 % Jeni


30 Jul 2018 13:56:41

...

Pelebaran begin cemen

Didit Prayitno


30 Jul 2018 13:53:01

...

Pasangan Batu saluran

Didit Prayitno


28 Jul 2018 19:24:30

...

Beton Fs 45 Sta 1+850

Jeni


28 Jul 2018 17:00:12

...

Tes slump

PT. CAHAYA UTAMA SENTOSA


28 Jul 2018 16:56:16

...

Beton FS 45 sta 1+750 (R)

Jeni


28 Jul 2018 07:01:34

...

Opname Beton FS 45

Jeni


28 Jul 2018 02:56:21

...

Saluran STA 1+325

Jeni


27 Jul 2018 11:46:37

...

Pasangan batu saluran sta 1+250

Jeni


27 Jul 2018 06:40:51

...

Penutupan beton dengan geotextile ST 1+600

Jeni


26 Jul 2018 22:09:27

...

cor Pelebaran jalan STA 1+600 (R)

Jeni


26 Jul 2018 20:10:39

...

Beton Fs 45 sta 1+600 (R)

Jeni


26 Jul 2018 17:06:40

...

Beton FS 45 Sta 1+550

Jeni


26 Jul 2018 14:57:46

...

Pasangan sal batu

Didit Prayitno


26 Jul 2018 14:22:14

...

FS 45 Sta 1+500 (R)

Jeni


25 Jul 2018 08:57:33

...

Saluran Pas. Batu Sta 1+250 ( Kiri )

Jeni


25 Jul 2018 07:47:22

...

Plesteran saluran pas. Batu

Jeni


25 Jul 2018 05:04:40

...

Urugan bahu jalan STA 0+700

Jeni


25 Jul 2018 04:46:55

...

Cor pelebaran jalan tadi pagi

Jeni


24 Jul 2018 22:15:49

...

Pengecoran FS 45 (kanan) sta 1+350

Jeni


24 Jul 2018 17:44:33

...

Pengecoran FS 45 (kanan) sta 1+250

Jeni


24 Jul 2018 16:13:58

...

Pengecoran FS 45 (kanan) STA 1+200

Jeni


24 Jul 2018 06:13:38

...

Progres minggu ke 10

Progress Pengerjaan: 71 % PT. CAHAYA UTAMA SENTOSA


23 Jul 2018 05:13:36

...

Persiapan beton lc

Didit Prayitno


23 Jul 2018 04:53:18

...

Pasanvan batu saluran

Jeni


22 Jul 2018 15:52:22

...

Pengecoran fs 45 sta 0+950

PT. CAHAYA UTAMA SENTOSA


22 Jul 2018 15:50:06

...

Sta 0+950 sampel fs tgl 22 juli 2018

Jeni


21 Jul 2018 08:31:56

...

Pekerjaan beton semen

Jeni


20 Jul 2018 15:14:51

...

Cor FS sta 0+800

Jeni


20 Jul 2018 03:13:08

...

Pasangan batu saluran (siaran)

Jeni


20 Jul 2018 01:27:29

...

Pasangan batu saluran

Progress Pengerjaan: 53 % PT. CAHAYA UTAMA SENTOSA


19 Jul 2018 13:01:46

...

PT. CAHAYA UTAMA SENTOSA


19 Jul 2018 12:51:23

...

Pasangan batu saluran sta 1+250

Jeni


19 Jul 2018 12:50:51

...

Cor LC sta 0+780-0+850

Jeni


19 Jul 2018 12:46:31

...

Galian pelebaran STA 2+400 Kanan

Jeni


19 Jul 2018 02:33:36

...

Didit Prayitno


18 Jul 2018 19:01:54

...

Pengecoran FA (kanan) Sta 0+650

Jeni


18 Jul 2018 14:03:01

...

Galian pelebaran (kanan)sta 2+350, pasangan batu saluran (kiri)1+250,

Progress Pengerjaan: 53 % Jeni


18 Jul 2018 06:53:15

...

Galian pelebaran sta 2+375 ( R )

Jeni


PENINGKATAN KAPASITAS JALAN PAGEMBRUNGAN - PENGADEGAN (DAK)

Kontraktor : PT. CAHAYA UTAMA SENTOSA
Jangka Waktu Selesai : 120 Hari
Mulai Pengerjaan : 18 May 2018
Selesai Pengerjaan : 14 Sep 2018
Deskripsi Progress : Pemeriksaan PHO

Progress Pengerjaan

100 %