GAMBAR PROGRES PENGERJAAN

RIWAYAT PENGERJAAN PAKET KEGIATAN

02 Oct 2018 04:10:18

...

Core drill

Progress Pengerjaan: 100 % Sulis


12 Sep 2018 06:36:30

...

Core drill

Sulis


12 Sep 2018 06:36:07

...

Sulis


04 Sep 2018 03:27:35

...

pembesian

Sulis


30 Aug 2018 14:48:30

...

Pengecoran

Sulis


30 Aug 2018 07:13:38

...

pembesian

Sulis


30 Aug 2018 03:37:59

...

Pekerjaan penulangan

Tri Pitoyo


29 Aug 2018 07:47:47

...

pembesian

Sulis


28 Aug 2018 14:21:52

...

Cor beton fs 45...lembur malam

Progress Pengerjaan: 75 % Sulis


27 Aug 2018 13:13:54

...

Perawatan beton dan persiapan cor beton

Sulis


21 Aug 2018 13:42:35

...

Cutting permukaan aspal yg rusak

Progress Pengerjaan: 52 % Sulis


16 Aug 2018 06:38:57

...

perawatan beton

Sulis


15 Aug 2018 06:26:11

...

Pemeliharaan beton

Sulis


09 Aug 2018 12:08:10

...

Pemeliharaan beton

Sulis


08 Aug 2018 08:45:38

...

Pemeliharaan beton

Sulis


07 Aug 2018 02:38:15

...

Pemeliharaan beton

Progress Pengerjaan: 52 % Sulis


06 Aug 2018 10:24:24

...

Pemeliharaan beton

Sulis


03 Aug 2018 08:37:59

...

Pemeliharaan beton

Sulis


02 Aug 2018 13:06:12

...

Penyemprotan curing compound

Sulis


02 Aug 2018 06:12:54

...

Perawatan beton

Sulis


31 Jul 2018 05:48:50

...

perataan badan jalan

Sulis


30 Jul 2018 08:48:52

...

Akhir pelebaran

Progress Pengerjaan: 48 % Sulis


30 Jul 2018 08:04:18

...

perawatan beton

Sulis


30 Jul 2018 06:11:47

...

perawatan beton

Sulis


28 Jul 2018 06:04:42

...

Pemeliharaan beton

Sulis


27 Jul 2018 09:08:06

...

Pemeliharaan beton

Sulis


26 Jul 2018 06:14:29

...

beton akhir

Sulis


25 Jul 2018 09:08:03

...

Perawatan beton dengan geotekstil

Tri Pitoyo


25 Jul 2018 04:30:33

...

Separuh badan jalan sudah selesai, dilanjut menunggu umur beton

Sulis


23 Jul 2018 12:55:07

...

Cor beton fs 45

Progress Pengerjaan: 46 % Sulis


23 Jul 2018 11:58:27

...

Cor fs 45

Progress Pengerjaan: 30 % Sulis


21 Jul 2018 03:26:31

...

Pengecoran sta 1+700

Sulis


19 Jul 2018 12:48:25

...

Progress Pengerjaan: 25 % Sulis


19 Jul 2018 05:31:41

...

pembesian

Sulis


19 Jul 2018 04:49:39

...

Pekerjaan beton fs 45

Tri Pitoyo


18 Jul 2018 14:58:31

...

Menggelar fs'45

Sulis


18 Jul 2018 06:28:01

...

lantai kerja

Sulis


PENINGKATAN KAPASITAS JALAN KEMBANGAN - KARANGGEDANG (DAK)

Kontraktor : PT. PURNAMA PUTRA WIJAYA
Jangka Waktu Selesai : 120 Hari
Mulai Pengerjaan : 18 May 2018
Selesai Pengerjaan : 14 Sep 2018
Deskripsi Progress : Pekerjaan beton & core drill sdh selesai

Progress Pengerjaan

100 %