GAMBAR PROGRES PENGERJAAN

RIWAYAT PENGERJAAN PAKET KEGIATAN

11 Aug 2018 08:17:19

...

Core drill beton

Jeni


08 Aug 2018 04:12:25

...

Jeni


07 Aug 2018 08:32:47

...

Cutting beton

Jeni


02 Aug 2018 08:18:45

...

Cek slump fs 45 sta 12+000 antara penyedia jasa,konsultan dan produsen readymix

Jeni


02 Aug 2018 08:17:22

...

Fs45 sta 12+000

Jeni


02 Aug 2018 05:49:41

...

Pengecoran pelebaran sta 11+950

Jeni


01 Aug 2018 09:04:47

...

Rapat evaluasi di DPUPR

Jeni


01 Aug 2018 08:56:01

...

Fs 45...Sta 11+800an

Jeni


31 Jul 2018 04:49:41

...

Pemasangan boxculvert sta 10+475

Jeni


30 Jul 2018 09:05:08

...

Lantai kerja sta 11+750 an

Jeni


30 Jul 2018 08:38:54

...

Perapian galian pelebaran beton

Jeni


28 Jul 2018 08:39:01

...

Persiapan pengecoran fs'45

Progress Pengerjaan: 70 % Jeni


27 Jul 2018 22:21:44

...

Pengecoran fs'45

Jeni


27 Jul 2018 08:34:08

...

Pengetesan beton fs'45

Jeni


27 Jul 2018 07:22:14

...

pemindahan tiang telepon

Syarif Darmawan


27 Jul 2018 02:52:48

...

Galian Pelebaran

Jeni


26 Jul 2018 08:23:33

...

Galian

Jeni


26 Jul 2018 00:45:34

...

Cek ketebalan fs45

Jeni


26 Jul 2018 00:45:03

...

Fs45

Jeni


26 Jul 2018 00:26:19

...

Fs45 26 juli 2018 7.30

Jeni


25 Jul 2018 05:44:09

...

Galian pelebaran jalan

Jeni


24 Jul 2018 07:27:25

...

Pengecoran lantai kerja

Jeni


24 Jul 2018 06:00:15

...

Galian pelebaran

Jeni


21 Jul 2018 08:55:58

...

Pelebaran sisi kiri sta 9+950

Progress Pengerjaan: 51 % PT. EKA JAYA PURNAMA


20 Jul 2018 00:22:13

...

Beton pelebaran jalan

Progress Pengerjaan: 45 % PT. EKA JAYA PURNAMA


19 Jul 2018 03:38:07

...

pelaksanaan pengecoran fs45

Syarif Darmawan


PENINGKATAN KAPASITAS JALAN KARANGMONCOL - RAJAWANA (LANJUTAN) (DAK)

Kontraktor : PT. EKA JAYA PURNAMA
Jangka Waktu Selesai : 150 Hari
Mulai Pengerjaan : 18 May 2018
Selesai Pengerjaan : 14 Oct 2018
Deskripsi Progress : Rapat evaluasi DPU-PR

Progress Pengerjaan

100 %