GAMBAR PROGRES PENGERJAAN

RIWAYAT PENGERJAAN PAKET KEGIATAN

05 Oct 2018 08:52:38

...

TMC 100%

Jeni


08 Sep 2018 09:08:39

...

Coredrill beton

Progress Pengerjaan: 100 % Jeni


03 Sep 2018 03:57:07

...

Rapat evaluasi

Jeni


21 Aug 2018 13:48:11

...

Pekerjaan sealant

Jeni


20 Aug 2018 10:18:43

...

Pemeriksaan termin

Progress Pengerjaan: 99 % Jeni


09 Aug 2018 13:18:15

...

Coredril beton

PT. CAHAYA UTAMA SENTOSA


09 Aug 2018 09:07:47

...

Core drill beton

Jeni


08 Aug 2018 02:52:46

...

Curing compound beton

Jeni


07 Aug 2018 22:34:59

...

Cor beton fs 45 Sta Akhir

Jeni


07 Aug 2018 12:32:14

...

Opname pekerjaan pas. batu

Jeni


06 Aug 2018 07:59:29

...

Uji tarik besi di Unsoed

Jeni


04 Aug 2018 10:18:45

...

Pas. Batu talud Sta 0+500

Progress Pengerjaan: 91 % Jeni


04 Aug 2018 02:09:39

...

Pengecoran fs45...sta 1+500

PT. CAHAYA UTAMA SENTOSA


03 Aug 2018 22:11:28

...

Pengecoran beton fs 45 kanan

Jeni


03 Aug 2018 22:10:39

...

Pengecoran pelebaran R

Jeni


01 Aug 2018 21:05:13

...

Pengecoran sta 1+300

PT. CAHAYA UTAMA SENTOSA


01 Aug 2018 20:47:44

...

Pengecoran beton fs45 pelebaran sisi kanan

Jeni


31 Jul 2018 13:04:00

...

Pasangan batu saluran

Jeni


30 Jul 2018 15:28:33

...

Pas. Batu saluran

Jeni


30 Jul 2018 03:36:51

...

Pas. Bt saluran sta 1 + 044

Mahmud Hidayat


28 Jul 2018 12:50:26

...

Pasangan batu utk saluran

Progress Pengerjaan: 83 % Jeni


27 Jul 2018 20:09:53

...

Pengecoran beton fs 45 pelebaran

Jeni


27 Jul 2018 06:31:55

...

Galian pelebaran Sta Akhir

Jeni


26 Jul 2018 10:01:02

...

Pas. Batu belah talud

Jeni


24 Jul 2018 13:31:22

...

Pengecoran pelebaran beton fs 45

Jeni


24 Jul 2018 06:37:10

...

Uji laboratorium fs 45 di unsud

Jeni


24 Jul 2018 06:22:20

...

Test beton Fs di Unsoed

Jeni


23 Jul 2018 08:28:05

...

Pasangan batu talud sta 1+350 kanan

PT. CAHAYA UTAMA SENTOSA


21 Jul 2018 12:23:43

...

Pekerjaan pasangan batu

Progress Pengerjaan: 71 % Jeni


21 Jul 2018 08:11:29

...

Saluran gendong pas. Batu sta 1+530 an kanan jalan

Mahmud Hidayat


PENINGKATAN KAPASITAS JALAN BANDINGAN - KEJOBONG (LANJUTAN) (DAK)

Kontraktor : PT. CAHAYA UTAMA SENTOSA
Jangka Waktu Selesai : 150 Hari
Mulai Pengerjaan : 18 May 2018
Selesai Pengerjaan : 14 Oct 2018
Deskripsi Progress : Pemeriksaan PHO

Progress Pengerjaan

100 %