GAMBAR PROGRES PENGERJAAN

RIWAYAT PENGERJAAN PAKET KEGIATAN

08 Nov 2018 08:03:33

...

Progress Pengerjaan: 100 % Jeni


16 Oct 2018 08:17:43

...

Pekerjaan sisa retaining wall sisi pepedan 11 meter dan timbunan

Progress Pengerjaan: 94 % PT. REKAYA SEMESTA UTAMA


16 Sep 2018 08:56:16

...

Penulangan plat lantai dan oprit sisi pepedan

Mahmud Hidayat


16 Sep 2018 08:54:48

...

Mahmud Hidayat


31 Aug 2018 03:47:31

...

Begisting plat lantai jembatan bentang sisi tegalpingen

Jeni


31 Aug 2018 03:46:39

...

Angkur dudukan handrail

Jeni


27 Aug 2018 03:39:12

...

Pek. Pembesian sisi tegalpingen

Mahmud Hidayat


27 Aug 2018 03:38:23

...

Mahmud Hidayat


09 Aug 2018 05:37:13

...

Mahmud Hidayat


09 Aug 2018 05:36:18

...

Mahmud Hidayat


09 Aug 2018 05:36:01

...

Mahmud Hidayat


09 Aug 2018 05:35:26

...

Mahmud Hidayat


09 Aug 2018 05:35:03

...

Mahmud Hidayat


07 Aug 2018 07:41:44

...

Mahmud Hidayat


07 Aug 2018 07:41:17

...

Rapat evaluasi direksi dg penyedia jasa

Mahmud Hidayat


06 Aug 2018 06:19:01

...

Persiapan pemasangan bondex segmen tengah

Mahmud Hidayat


31 Jul 2018 06:26:54

...

Pemasangan bondex dan s. Conector

Mahmud Hidayat


27 Jul 2018 07:24:45

...

Pengurugan oprit sisi pepedan

Mahmud Hidayat


24 Jul 2018 03:48:43

...

Aktivitas pengencangan baut2

Mahmud Hidayat


22 Jul 2018 06:11:19

...

Erection baja jembatan

Progress Pengerjaan: 28 % Jeni


PEMBANGUNAN JEMBATAN KALI GINTUNG RUAS JALAN PEPEDAN - TEGALPINGEN

Kontraktor : PT. REKAYA SEMESTA UTAMA
Jangka Waktu Selesai : 150 Hari
Mulai Pengerjaan : 23 Apr 2018
Selesai Pengerjaan : 19 Sep 2018
Deskripsi Progress : Pemeriksaan PHO 5 Nopember 2018

Progress Pengerjaan

100 %