GAMBAR PROGRES PENGERJAAN

RIWAYAT PENGERJAAN PAKET KEGIATAN

14 Sep 2018 11:23:53

...

Core drill HRS-WC

Doni


08 Sep 2018 04:46:46

...

Kunjungan dari Bina Program

Progress Pengerjaan: 100 % Doni


07 Sep 2018 04:54:06

...

Mengukur pekerjaan HRS

Doni


06 Sep 2018 07:53:07

...

Pemadatan HRS

Doni


06 Sep 2018 07:52:00

...

Pekerjaan HRS sdh 100%

Doni


05 Sep 2018 14:27:12

...

Mengecek ketebalan HRS

Doni


05 Sep 2018 14:26:06

...

Pengambilan sempel HRS

Doni


05 Sep 2018 14:25:07

...

Peneumatic roller (PTR)

Doni


05 Sep 2018 14:23:06

...

Tendem roller

Doni


05 Sep 2018 14:22:00

...

Asphalt finisher

Doni


05 Sep 2018 14:20:47

...

Asphalt sprayer

Doni


05 Sep 2018 14:19:22

...

Compresor untuk pekerjaan HRS

Doni


03 Sep 2018 04:23:03

...

Rapat evaluasi di DPU-PR bidang Bina Marga

Doni


01 Sep 2018 03:47:52

...

Patching AC-base(L) tanpa finisher

Progress Pengerjaan: 61 % Doni


25 Aug 2018 07:37:15

...

Normalisasi saluran STA 0+050

Progress Pengerjaan: 55 % Doni


18 Aug 2018 15:11:27

...

Hampar fs 45 sta 1+050

Progress Pengerjaan: 51 % Doni


16 Aug 2018 05:37:36

...

Cor beton FS 45 STA 0+125 kiri

Doni


14 Aug 2018 19:09:59

...

Hampar fs45 sta 0+200 sebelah kiri

Doni


13 Aug 2018 12:10:05

...

Cek lapangan dengan PPTK

Doni


11 Aug 2018 09:36:33

...

Galian gorong-gorong plat beton STA 0+289

Doni


11 Aug 2018 07:10:20

...

Galian saluran STA 0+150

Progress Pengerjaan: 43 % Doni


10 Aug 2018 16:43:23

...

Vibrator beton FS 45 STA 0+450

Doni


10 Aug 2018 16:41:46

...

PENGECORAN FS 45 STA 0+450

Doni


10 Aug 2018 16:38:31

...

Slump FS 45 STA 0+450

Doni


10 Aug 2018 10:12:26

...

Pengujian kuat lentur FS45 di lab Unsoed

Doni


10 Aug 2018 10:10:29

...

Cutting beton STA 1+100 (8 Agustus 2018)

Doni


04 Aug 2018 11:41:45

...

Cek lebar galian pelebaran jalan STA 0+750

Progress Pengerjaan: 34 % Doni


03 Aug 2018 18:27:39

...

Membuat garis sta 0+950

Doni


03 Aug 2018 17:28:12

...

Cek ketebalan fs sta 0+950

Doni


02 Aug 2018 18:05:16

...

Hampar fs 45 di sta 0+450

Doni


02 Aug 2018 12:15:40

...

Cek rencana luasan patching

Doni


02 Aug 2018 06:54:40

...

Pemasangan bekisting saluran

Doni


01 Aug 2018 15:03:43

...

STA 1+100 , pek. FS 45

Doni


31 Jul 2018 08:21:14

...

LC STA 0+200

Doni


31 Jul 2018 07:30:27

...

Pengecekan galian pelebaran dan saluran STA 0+100

Doni


31 Jul 2018 03:47:01

...

Mahmud Hidayat


31 Jul 2018 03:46:31

...

Galian pelebaran sisi kiri full sta 0 +000 s.d 1 + 479

Mahmud Hidayat


29 Jul 2018 06:06:45

...

FS STA 1+300an

Doni


29 Jul 2018 06:06:05

...

Doni


28 Jul 2018 09:22:50

...

Pengukuran lebar area saluran rencana STA 1+000

Doni


27 Jul 2018 09:02:13

...

Pemeliharaan beton dgn penyiraman air di permukaan beton

Progress Pengerjaan: 24 % Doni


26 Jul 2018 22:47:06

...

Fs 45 STA 1+440 tgl 26/07/2018 (pagi)

Doni


26 Jul 2018 22:41:28

...

cor fs 45 STA 0+625 tgl 25/07/2018

Doni


25 Jul 2018 06:10:49

...

Curing compound beton sta 0+600an

Doni


25 Jul 2018 06:07:50

...

Fs 45 sta 0+600an

Doni


25 Jul 2018 06:06:14

...

Slump test sta 0+600an

Doni


25 Jul 2018 05:58:03

...

Doni


25 Jul 2018 05:50:02

...

Kordinasi lapangan dg salah satu anggota dewan.

Mahmud Hidayat


23 Jul 2018 09:25:51

...

Doni


21 Jul 2018 08:05:03

...

Pekerjaan hari ini 21/7/2018 : Galian pasangan batu, pas. Batu saluran dan LC

Progress Pengerjaan: 20 % Doni


21 Jul 2018 07:52:52

...

Saluran beton sta 1 + 250an kanan jalan

Mahmud Hidayat


21 Jul 2018 02:28:41

...

Fs tanggal 19 Juli 2018

Progress Pengerjaan: 18 % Doni


PENINGKATAN KAPASITAS JALAN KEJOBONG - TIMBANG (LANJUTAN) (DAK)

Kontraktor : PT. SURYA HUTAMA KARYA
Jangka Waktu Selesai : 150 Hari
Mulai Pengerjaan : 18 May 2018
Selesai Pengerjaan : 14 Oct 2018
Deskripsi Progress : Cek ketebalan HRS-WC

Progress Pengerjaan

100 %