GAMBAR PROGRES PENGERJAAN

RIWAYAT PENGERJAAN PAKET KEGIATAN

31 Oct 2018 11:21:38

...

Novi


25 Oct 2018 14:08:19

...

Novi


24 Oct 2018 14:18:04

...

Novi


23 Oct 2018 07:37:04

...

Novi


18 Oct 2018 16:39:11

...

Novi


09 Oct 2018 11:28:24

...

Novi


19 Sep 2018 10:03:34

...

Novi


15 Sep 2018 12:41:03

...

Novi


13 Sep 2018 16:32:38

...

Novi


12 Sep 2018 06:22:04

...

Progress Pengerjaan: 23 % Novi


10 Sep 2018 07:32:03

...

Novi


10 Sep 2018 07:31:39

...

Novi


07 Sep 2018 06:58:08

...

Novi


05 Sep 2018 15:07:43

...

Novi


04 Sep 2018 14:58:27

...

Novi


03 Sep 2018 08:03:25

...

Novi


30 Aug 2018 10:11:09

...

Novi


30 Aug 2018 00:04:41

...

Novi


28 Aug 2018 07:00:41

...

Novi


27 Aug 2018 16:52:16

...

Novi


25 Aug 2018 16:59:57

...

Novi


24 Aug 2018 12:58:10

...

Novi


24 Aug 2018 01:02:48

...

Novi


21 Aug 2018 06:43:29

...

Novi


20 Aug 2018 14:20:09

...

Didit Prayitno


20 Aug 2018 14:19:30

...

Didit Prayitno


20 Aug 2018 04:35:35

...

Progress Pengerjaan: 12 % Novi


20 Aug 2018 04:35:12

...

12,31

Novi


16 Aug 2018 02:37:12

...

Novi


14 Aug 2018 16:51:43

...

Novi


11 Aug 2018 11:39:08

...

Novi


10 Aug 2018 12:42:43

...

Progress Pengerjaan: 11 % CV. CENTRAL TEKNIK


10 Aug 2018 10:24:40

...

Novi


09 Aug 2018 16:17:02

...

Novi


06 Aug 2018 09:52:55

...

pemasang pembesian saluran

Novi


04 Aug 2018 15:37:23

...

Progress Pengerjaan: 10 % Novi


03 Aug 2018 08:17:39

...

Novi


03 Aug 2018 08:17:11

...

Galian saluran

Novi


03 Aug 2018 08:16:39

...

Pemasangan bekisting

Novi


03 Aug 2018 08:16:36

...

Pemasangan bekisting

Novi


02 Aug 2018 05:21:19

...

Pengecoran Saluran

Novi


02 Aug 2018 05:20:26

...

Novi


02 Aug 2018 04:54:33

...

Novi


31 Jul 2018 08:54:39

...

Pemasangan besi saluran

Novi


30 Jul 2018 07:41:40

...

Pemasangan Paving

Novi


27 Jul 2018 10:03:27

...

Novi


26 Jul 2018 14:55:35

...

Galian pas. Sal existing

Didit Prayitno


26 Jul 2018 08:51:29

...

Pemasangan pembesian saluran

Novi


25 Jul 2018 08:35:57

...

Pemasangan tutup saluran beton

Novi


24 Jul 2018 06:55:03

...

Novi


21 Jul 2018 07:02:15

...

Drainase

Didit Prayitno


21 Jul 2018 07:01:21

...

Drainase saluran

Didit Prayitno


19 Jul 2018 13:08:05

...

Progress Pengerjaan: 8 % Novi


19 Jul 2018 04:20:05

...

Progress Pengerjaan: 8 % CV. CENTRAL TEKNIK


19 Jul 2018 03:41:52

...

Pekerjaan Galian

Novi


REVITALISASI DRAINASE SEKUNDER SOEDIRMAN - KALI GRINGSING

Kontraktor : CV. CENTRAL TEKNIK
Jangka Waktu Selesai : 150 Hari
Mulai Pengerjaan : 15 May 2018
Selesai Pengerjaan : 11 Oct 2018
Deskripsi Progress :

Progress Pengerjaan

23 %