GAMBAR PROGRES PENGERJAAN

RIWAYAT PENGERJAAN PAKET KEGIATAN

04 Aug 2018 06:19:36

...

Coredrill

Wasis


01 Aug 2018 03:23:54

...

Wasis


01 Aug 2018 03:23:14

...

Cuting

Wasis


31 Jul 2018 02:28:02

...

Cutting

Wasis


31 Jul 2018 02:23:57

...

Cuting beton

Wasis


28 Jul 2018 01:49:54

...

Full pelebaran 6 meter

Wasis


28 Jul 2018 01:48:32

...

Lemburr terusss

Wasis


28 Jul 2018 01:47:55

...

Lembur kemrin pagi

Wasis


28 Jul 2018 01:46:15

...

07.35 belum ada pekerja pengecoran beton full

Progress Pengerjaan: 97 % Wasis


27 Jul 2018 06:39:09

...

Pelebaran beton yang bekistingnya menceng di bongkar dan perlu perapian

Wasis


26 Jul 2018 13:50:59

...

Tetap stand by tetap semangat mengejar progres.

Wasis


26 Jul 2018 01:55:11

...

Pagi ini di beri penutup beton

Wasis


25 Jul 2018 12:39:44

...

Mbekisting LURUS

Wasis


25 Jul 2018 07:23:07

...

24- juli 2018 pengecoran malam hari

Wasis


24 Jul 2018 11:59:40

...

Selaganggeng - pengalusan mulai corr lagi

Wasis


23 Jul 2018 03:54:23

...

Di sirami pak

Wasis


21 Jul 2018 06:56:50

...

Pengecoran tadi pagi 62.5 m3. Sisa pekerjaan tinggal lantai kerja dan beton pelebaran saja pak. Proges saat ini masih minus 8

Progress Pengerjaan: 30 % Wasis


20 Jul 2018 17:09:10

...

Progres menyusul jumat 20 - juli pengecoran jam 22 - 00.08. 0.25x1x290 meter

Wasis


20 Jul 2018 13:13:43

...

Pembongkaran bekisting yang kurang rapi pak akan di luruskan pengecoran hanya bisa mlm hari . di karnakan lalu lalang kendaraan umum

Wasis


20 Jul 2018 13:11:10

...

Siap cor pak progres menyusul . lantai kerja di gosok rapi

Wasis


PELEBARAN JALAN SELAGANGGENG - PENGALUSAN

Kontraktor : CV. INDESCO DEVELOPER
Jangka Waktu Selesai : 120 Hari
Mulai Pengerjaan : 15 May 2018
Selesai Pengerjaan : 11 Sep 2018
Deskripsi Progress : Sudah tmc sudah pemriksaan dan sudah Pho

Progress Pengerjaan

100 %