GAMBAR PROGRES PENGERJAAN

RIWAYAT PENGERJAAN PAKET KEGIATAN

04 Nov 2018 13:47:31

...

median jalan selesai

Andi


29 Oct 2018 09:29:00

...

pekerjaan trotoar

Progress Pengerjaan: 82 % Andi


25 Oct 2018 05:33:17

...

Andi


25 Oct 2018 05:32:59

...

pekerjaan thermoplastik (marka jalan)

Andi


17 Oct 2018 01:58:25

...

pekerjaan trotoar

Andi


08 Oct 2018 23:20:58

...

Andi


04 Oct 2018 01:25:21

...

median jalan

Progress Pengerjaan: 53 % Andi


02 Oct 2018 03:18:21

...

Widayanto


01 Sep 2018 07:39:22

...

Pemasangan kanstin median

Andi


18 Aug 2018 07:24:31

...

Widayanto


18 Aug 2018 07:23:53

...

Dipercepat tambahi tenaganya tuk trotoar n median. Waktu dpertimbangkan

Widayanto


13 Aug 2018 05:17:18

...

Median jalan

Progress Pengerjaan: 28 % Andi


02 Aug 2018 03:28:32

...

Pek. Trotoar

Andi


01 Aug 2018 02:44:10

...

Kansteen trotoar

Progress Pengerjaan: 13 % Andi


30 Jul 2018 04:27:06

...

Mohon tenaga ditambah tu trotoar baru dikit dkerjakn. Perhatikan waktu n cuaca . Yg median mohon dikerjakan dipapak dari utara jad aga group pekerja lag

Widayanto


30 Jul 2018 03:25:31

...

Kansteen trotoar

Andi


22 Jul 2018 13:58:46

...

Kansteen median jalan

Progress Pengerjaan: 5 % Andi


22 Jul 2018 03:58:55

...

Median kol sugiri bbtsari

Widayanto


21 Jul 2018 23:57:56

...

Median kolonl sugiri bbtsari

Widayanto


19 Jul 2018 10:10:12

...

Kerjaan median jalan (pasangan kansteen)

Widayanto


19 Jul 2018 09:23:42

...

Median jalan

Progress Pengerjaan: 4 % Andi


REVITALISASI MEDIAN DAN TROTOAR JALAN KOLONEL SUGIRI BOBOTSARI

Kontraktor : CV. PERMATA
Jangka Waktu Selesai : 150 Hari
Mulai Pengerjaan : 15 May 2018
Selesai Pengerjaan : 11 Oct 2018
Deskripsi Progress : pekerjaan trotoar terus di kebut

Progress Pengerjaan

85 %