GAMBAR PROGRES PENGERJAAN

RIWAYAT PENGERJAAN PAKET KEGIATAN

31 Oct 2018 18:18:45

...

Progress Pengerjaan: 77 % Novi


25 Oct 2018 21:08:58

...

Novi


24 Oct 2018 21:24:08

...

Novi


09 Oct 2018 18:28:09

...

Novi


09 Oct 2018 18:27:52

...

Novi


09 Oct 2018 10:25:08

...

CV. BERKAH MULYA


09 Oct 2018 01:57:09

...

CV. BERKAH MULYA


09 Oct 2018 01:56:04

...

CV. BERKAH MULYA


09 Oct 2018 01:54:28

...

CV. BERKAH MULYA


09 Oct 2018 01:53:52

...

CV. BERKAH MULYA


03 Oct 2018 12:01:05

...

Progress Pengerjaan: 68 % Novi


28 Sep 2018 08:52:19

...

CV. BERKAH MULYA


28 Sep 2018 08:51:45

...

CV. BERKAH MULYA


27 Sep 2018 23:55:10

...

Novi


27 Sep 2018 23:54:59

...

Novi


27 Sep 2018 19:12:06

...

CV. BERKAH MULYA


26 Sep 2018 20:36:54

...

Novi


21 Sep 2018 22:21:21

...

Novi


20 Sep 2018 21:03:17

...

Novi


19 Sep 2018 17:03:09

...

Novi


19 Sep 2018 15:01:18

...

Novi


18 Sep 2018 08:31:16

...

Novi


18 Sep 2018 07:11:04

...

CV. BERKAH MULYA


18 Sep 2018 07:10:31

...

CV. BERKAH MULYA


18 Sep 2018 07:09:54

...

CV. BERKAH MULYA


15 Sep 2018 19:41:24

...

Novi


13 Sep 2018 23:32:55

...

Novi


05 Sep 2018 22:07:23

...

Novi


04 Sep 2018 21:56:54

...

Novi


30 Aug 2018 17:12:05

...

Novi


30 Aug 2018 07:04:16

...

Novi


24 Aug 2018 19:57:41

...

Novi


21 Aug 2018 10:29:43

...

CV. BERKAH MULYA


16 Aug 2018 09:36:35

...

Novi


14 Aug 2018 23:51:24

...

Novi


11 Aug 2018 18:38:12

...

Novi


10 Aug 2018 17:12:29

...

CV. BERKAH MULYA


10 Aug 2018 17:11:20

...

CV. BERKAH MULYA


10 Aug 2018 16:52:53

...

Novi


09 Aug 2018 23:18:27

...

Novi


06 Aug 2018 16:52:20

...

Novi


06 Aug 2018 16:51:58

...

Pengecoran pelebaran

Novi


04 Aug 2018 22:43:25

...

Progress Pengerjaan: 19 % Novi


03 Aug 2018 14:27:45

...

Novi


03 Aug 2018 14:26:30

...

galian untuk box culvert

Novi


03 Aug 2018 14:20:11

...

Novi


03 Aug 2018 14:19:44

...

pengecoran saluran

Novi


03 Aug 2018 07:18:28

...

Pemasangan bok culvert

Sukirman


02 Aug 2018 12:20:46

...

Pengecoran Saluran Beton

Novi


02 Aug 2018 11:53:26

...

Novi


31 Jul 2018 15:57:46

...

Cor Saluran

Novi


30 Jul 2018 13:58:39

...

Galian Box Culvert

Novi


28 Jul 2018 15:02:11

...

Progress Pengerjaan: 15 % Novi


27 Jul 2018 17:02:48

...

Novi


26 Jul 2018 14:27:06

...

Galian untuk box culvert

Novi


25 Jul 2018 12:40:37

...

Galian saluran

Novi


24 Jul 2018 10:32:45

...

Novi


21 Jul 2018 14:17:01

...

Pekerjaan perapian saluran

Sukirman


19 Jul 2018 14:39:19

...

Progress Pengerjaan: 15 % Novi


PENINGKATAN KAPASITAS JALAN SELAGANGGENG - MANGUNEGARA (LANJUTAN) (DAK)

Kontraktor : CV. BERKAH MULYA
Jangka Waktu Selesai : 150 Hari
Mulai Pengerjaan : 15 May 2018
Selesai Pengerjaan : 11 Oct 2018
Deskripsi Progress :

Progress Pengerjaan

77 %