GAMBAR PROGRES PENGERJAAN

RIWAYAT PENGERJAAN PAKET KEGIATAN

19 Sep 2018 14:55:23

...

Menghampar Aspal Produk, AC Base (L)

Ugut


05 Sep 2018 12:14:10

...

Pek pasangan batu

Ugut


05 Sep 2018 12:13:18

...

Pas batu selesai,

Progress Pengerjaan: 10 % Ugut


30 Aug 2018 13:39:53

...

Ugut


30 Aug 2018 13:38:42

...

Finishing pas batu

Ugut


27 Aug 2018 14:27:36

...

Finishing pas batu

Progress Pengerjaan: 9 % Ugut


25 Aug 2018 17:24:23

...

Pelaksana lapangan

Ugut


25 Aug 2018 17:23:02

...

Finishing pek pas batu

Ugut


18 Aug 2018 13:40:54

...

Pekerjaan galian & pas batu

Ugut


16 Aug 2018 15:25:00

...

Pasangan batu terpasang

Ugut


16 Aug 2018 15:21:48

...

Pek pasangan batu

Ugut


16 Aug 2018 15:06:27

...

Inspektor

Ugut


13 Aug 2018 10:38:27

...

Pek pasangan batu

Ugut


13 Aug 2018 10:31:19

...

Pek pasangan batu

Ugut


10 Aug 2018 13:27:21

...

Pek. bowplank & galian utk pondasi

Ugut


10 Aug 2018 13:24:55

...

Inspektor

Ugut


09 Aug 2018 11:44:17

...

Inspektor

Ugut


PENINGKATAN JALAN PALUMBUNGAN WETAN - DAGAN

Kontraktor : CV. PUTRA MANDIRI
Jangka Waktu Selesai : 90 Hari
Mulai Pengerjaan : 27 Jul 2018
Selesai Pengerjaan : 24 Oct 2018
Deskripsi Progress : Telah selesai overlay produk aspal HRS-WC dan sudah dilakukan coredrill dilapangan

Progress Pengerjaan

100 %