GAMBAR PROGRES PENGERJAAN

RIWAYAT PENGERJAAN PAKET KEGIATAN

02 Oct 2018 12:12:58

...

Pekerjaan latasir

Progress Pengerjaan: 98 % Ugut


12 Sep 2018 09:44:52

...

Lapen 12 sept

Ugut


12 Sep 2018 09:44:33

...

Pekrjaan lapen 12 sept

Ugut


12 Sep 2018 09:44:03

...

Insp. 10 sept

Ugut


12 Sep 2018 09:43:40

...

Pekerjaan latasir 10sept

Ugut


04 Sep 2018 19:46:02

...

Inspektor

Ugut


04 Sep 2018 19:32:02

...

Pekerjaan latasir

Ugut


04 Sep 2018 19:31:12

...

Pekerjaan lapen

Ugut


04 Sep 2018 19:30:55

...

Ugut


03 Sep 2018 09:52:44

...

Pekerjaan lapen

Progress Pengerjaan: 59 % Ugut


30 Aug 2018 21:18:51

...

Ugut


29 Aug 2018 20:54:25

...

Ugut


29 Aug 2018 20:53:55

...

Pekerjaan lapen

Ugut


25 Aug 2018 10:44:31

...

7,2

Ugut


25 Aug 2018 10:42:18

...

Pathing 24 agustus

Ugut


23 Aug 2018 22:05:13

...

Inspektor

Ugut


23 Aug 2018 22:02:32

...

Perbaikan dan pembuatan gorong2

Ugut


21 Aug 2018 22:48:41

...

Ugut


21 Aug 2018 22:47:54

...

Pekerjaan lapen

Ugut


21 Aug 2018 10:08:21

...

Inspektor tgl 21 agustus

Ugut


21 Aug 2018 10:07:51

...

Pekerjaan lapen

Ugut


14 Aug 2018 19:14:46

...

Ugut


14 Aug 2018 19:14:35

...

Ugut


13 Aug 2018 16:08:19

...

Progress Pengerjaan: 6 % Ugut


13 Aug 2018 16:07:16

...

Ugut


13 Aug 2018 16:06:46

...

Ugut


11 Aug 2018 17:18:22

...

Persiapan pekerjaan perkerasan jalan

Ugut


10 Aug 2018 17:18:41

...

Ugut


10 Aug 2018 17:18:28

...

Finishing saluran

Ugut


10 Aug 2018 17:18:02

...

Ugut


09 Aug 2018 13:45:41

...

Ugut


09 Aug 2018 09:08:55

...

3,2

Ugut


09 Aug 2018 09:08:27

...

Ugut


04 Aug 2018 19:51:07

...

Ugut


04 Aug 2018 19:50:53

...

Persiapan pekerjaan talud

Ugut


04 Aug 2018 06:10:40

...

Ugut


02 Aug 2018 20:54:22

...

Ugut


02 Aug 2018 20:51:22

...

Persiapan bongkaran gorong2 rusak

Ugut


02 Aug 2018 19:28:44

...

Pekerjaan talud sta 0+500

Ugut


31 Jul 2018 14:44:36

...

Ugut


28 Jul 2018 15:51:27

...

Ugut


28 Jul 2018 15:51:11

...

Ugut


26 Jul 2018 14:55:08

...

Ugut


26 Jul 2018 14:54:50

...

Ugut


26 Jul 2018 14:54:27

...

Ugut


25 Jul 2018 19:57:36

...

STA 0+200

CV. PRIMA KINARYA


25 Jul 2018 19:57:13

...

STA 0+200

CV. PRIMA KINARYA


25 Jul 2018 19:55:59

...

STA 0+200

CV. PRIMA KINARYA


25 Jul 2018 14:37:07

...

Ugut


25 Jul 2018 14:36:31

...

Langsira di beberapa titik pekerjaan

Ugut


25 Jul 2018 11:45:07

...

Inspector tgl 24

Ugut


24 Jul 2018 15:23:30

...

Langsir aspal

Ugut


24 Jul 2018 15:22:59

...

Ugut


21 Jul 2018 14:37:46

...

CV. PRIMA KINARYA


21 Jul 2018 14:33:46

...

STA 1+400

CV. PRIMA KINARYA


21 Jul 2018 14:33:12

...

STA 1+200

CV. PRIMA KINARYA


21 Jul 2018 14:27:21

...

STA 0+800

CV. PRIMA KINARYA


21 Jul 2018 14:24:56

...

STA 0+700

CV. PRIMA KINARYA


21 Jul 2018 14:23:28

...

STA 0+600

CV. PRIMA KINARYA


21 Jul 2018 14:22:01

...

STA 0+500

CV. PRIMA KINARYA


21 Jul 2018 14:21:13

...

STA 0+400

CV. PRIMA KINARYA


21 Jul 2018 14:17:57

...

STA 0+150

CV. PRIMA KINARYA


21 Jul 2018 14:16:07

...

STA 1+500

CV. PRIMA KINARYA


21 Jul 2018 14:15:06

...

STA 1+500

CV. PRIMA KINARYA


21 Jul 2018 13:50:28

...

Langsiran ke masing2 titik pekerjaan

Progress Pengerjaan: 1 % Ugut


21 Jul 2018 13:49:12

...

Ugut


21 Jul 2018 13:48:43

...

Ugut


19 Jul 2018 19:45:10

...

Inspektor

Ugut


19 Jul 2018 19:43:22

...

Material dilokasi kegiatan

Ugut


19 Jul 2018 19:41:39

...

Langsiran material

Ugut


19 Jul 2018 14:02:09

...

Dropping material

Tri Pitoyo


PENINGKATAN JALAN CURUG KARANG-TANALUM

Kontraktor : CV. PRIMA KINARYA
Jangka Waktu Selesai : 150 Hari
Mulai Pengerjaan : 25 Jun 2018
Selesai Pengerjaan : 21 Nov 2018
Deskripsi Progress : Inspektor

Progress Pengerjaan

98 %