GAMBAR PROGRES PENGERJAAN

RIWAYAT PENGERJAAN PAKET KEGIATAN

09 Oct 2018 17:28:08

...

TMC

Deni


09 Oct 2018 17:27:35

...

TMC

Deni


06 Oct 2018 19:24:40

...

Pekerjaan kurang cat leuning gorong gorong

Deni


06 Oct 2018 19:22:11

...

Deni


06 Oct 2018 19:21:55

...

Pekerjaan kurang leuning gorong gorong

Progress Pengerjaan: 98 % Deni


02 Oct 2018 18:19:13

...

Rapat evaluasi rutin awal bulan

Deni


01 Oct 2018 15:34:55

...

Siar talud

Deni


29 Sep 2018 16:58:24

...

Deni


29 Sep 2018 16:57:56

...

Lepaan talud penambahan hasil opname

Progress Pengerjaan: 95 % Deni


28 Sep 2018 15:47:26

...

Penambahan talud hasil opnam

Deni


27 Sep 2018 16:46:21

...

Deni


27 Sep 2018 16:45:59

...

Penambahan talud hasil opname

Deni


26 Sep 2018 19:31:20

...

Deni


26 Sep 2018 19:30:42

...

Core drill

Deni


24 Sep 2018 15:46:05

...

Deni


24 Sep 2018 15:45:52

...

Overlay HRS

Deni


21 Sep 2018 20:39:14

...

Deni


21 Sep 2018 20:39:03

...

Penambahan talud

Deni


20 Sep 2018 18:12:22

...

Deni


19 Sep 2018 11:23:32

...

Deni


19 Sep 2018 11:23:12

...

Penambahan talud hasil opname

Deni


18 Sep 2018 14:46:03

...

Deni


18 Sep 2018 14:45:51

...

Penambahan talud hasil opname

Deni


17 Sep 2018 12:20:50

...

Deni


17 Sep 2018 12:20:35

...

Galian tanah tambahan pas. Talud hasil opname

Deni


15 Sep 2018 16:49:34

...

Deni


15 Sep 2018 16:49:07

...

Pasangan batu belah

Deni


14 Sep 2018 19:11:18

...

Deni


14 Sep 2018 19:10:57

...

Galian tanah sebelah kanan

Deni


13 Sep 2018 09:42:11

...

Tambahan talud hasil opname

Deni


12 Sep 2018 14:44:34

...

Pemeriksaan termin 50

Deni


10 Sep 2018 19:57:43

...

Mohon maaf.. Abaikan foto dua tadi, karena salah lokasi.. Tertanda Inspektor

Deni


10 Sep 2018 19:07:47

...

Deni


10 Sep 2018 19:07:37

...

Galian drainnase

Deni


10 Sep 2018 19:05:15

...

Hari ini Tidak ada pekerjaan

Deni


08 Sep 2018 15:35:09

...

Seminggu libur tdk ad pekerjaan

Deni


06 Sep 2018 15:55:13

...

Tidak ada pekerjaan

Deni


05 Sep 2018 15:03:07

...

Hari ini tidak ada pekerjaan

Deni


03 Sep 2018 14:41:05

...

Lahan siap overlay

Mahmud Hidayat


03 Sep 2018 13:33:24

...

Rapat awal bulan Bina Marga

Deni


01 Sep 2018 15:13:19

...

Tinggal nunggu HRS dan mengulang pemadatan urugan tanah

Deni


01 Sep 2018 15:12:29

...

Finishing leuning

Progress Pengerjaan: 74 % Deni


31 Aug 2018 11:35:08

...

Deni


31 Aug 2018 11:34:55

...

Deni


31 Aug 2018 11:34:33

...

Hari ini pekerjaan terakhir.. Tinggal nunggu overlay HRS

Deni


30 Aug 2018 17:03:46

...

Lanjut finishing talud

Deni


30 Aug 2018 17:03:15

...

Lanjut patching lapen

Deni


29 Aug 2018 14:39:21

...

Deni


29 Aug 2018 14:38:59

...

Patching lapen

Deni


28 Aug 2018 11:53:28

...

Deni


28 Aug 2018 11:53:13

...

Urugan per layer distamper

Deni


27 Aug 2018 12:09:33

...

Deni


27 Aug 2018 12:08:44

...

Finising talud

Deni


25 Aug 2018 17:04:41

...

Deni


25 Aug 2018 17:04:25

...

Persiapan cor siklop

Progress Pengerjaan: 69 % Deni


24 Aug 2018 17:08:41

...

Pembesian pelebaran gorong2 STA 0 +00

Deni


24 Aug 2018 15:27:45

...

Deni


24 Aug 2018 15:27:31

...

Pembesian jembatan STA 0+000

Deni


23 Aug 2018 15:11:25

...

Cor plat gorong2 Sta 0+405

Deni


21 Aug 2018 11:57:22

...

Deni


21 Aug 2018 11:57:02

...

Pembesian jembatan STA 0+405

Deni


20 Aug 2018 12:35:40

...

Deni


20 Aug 2018 12:35:28

...

Rabat balok landas jembatan STA 0+405

Deni


18 Aug 2018 17:09:01

...

Progress Pengerjaan: 65 % Deni


18 Aug 2018 10:46:40

...

Deni


18 Aug 2018 10:42:28

...

Sier STA 0+350

Deni


16 Aug 2018 13:45:42

...

Deni


16 Aug 2018 13:45:25

...

Lepaan STA 0+445

Deni


15 Aug 2018 14:44:34

...

Deni


15 Aug 2018 14:44:18

...

Plester talud STA 0+400

Deni


14 Aug 2018 11:49:39

...

Pasang batu STA 0+445 sebelah kanan

Deni


14 Aug 2018 11:48:22

...

Finising talud STA 0+445

Deni


13 Aug 2018 15:37:43

...

Deni


13 Aug 2018 15:37:15

...

Begisting gorong" kedua

Deni


13 Aug 2018 13:56:48

...

Gorong2 plat sta 0 + 540

Mahmud Hidayat


11 Aug 2018 13:50:06

...

Deni


11 Aug 2018 13:49:10

...

Pasangan STA 0+445

Progress Pengerjaan: 55 % Deni


10 Aug 2018 12:59:37

...

Deni


10 Aug 2018 12:58:51

...

Pasang begisting gorong" pertama

Deni


09 Aug 2018 12:29:41

...

Deni


09 Aug 2018 12:29:20

...

Pasang batu belah

Deni


08 Aug 2018 14:31:01

...

Deni


08 Aug 2018 14:30:55

...

Finishing talud

Deni


07 Aug 2018 12:09:53

...

Deni


07 Aug 2018 12:09:27

...

Gali tanah

Deni


07 Aug 2018 11:08:05

...

Deni


07 Aug 2018 11:07:39

...

Deni


07 Aug 2018 11:07:16

...

Rencana pelebaran gorong2 STA 0+00

Deni


06 Aug 2018 12:51:56

...

Deni


06 Aug 2018 12:51:19

...

Pasang pondasi gorong" ke dua

Deni


05 Aug 2018 18:56:42

...

Progress Pengerjaan: 49 % Deni


04 Aug 2018 14:45:34

...

STA 0.405 pas gorong" pertama

Deni


04 Aug 2018 14:44:21

...

Pengukuran bowplank talud STA 0.

Deni


03 Aug 2018 14:07:44

...

Deni


03 Aug 2018 14:06:27

...

Pasangan batu STA +0.400 deket gorong" 1

Deni


02 Aug 2018 13:16:01

...

Deni


02 Aug 2018 13:15:08

...

Pasangan batu belah STA +0.350

Deni


01 Aug 2018 13:34:15

...

Pasang batu pondasi pada jembatan STA 0.405

Deni


31 Jul 2018 15:43:59

...

Deni


31 Jul 2018 15:43:14

...

Pasangan batu STA 0.350

Deni


30 Jul 2018 14:36:55

...

Deni


30 Jul 2018 14:36:21

...

Pasangan batu belah STA 0.300 kanan

Deni


30 Jul 2018 10:39:46

...

Mahmud Hidayat


28 Jul 2018 15:58:38

...

Progress Pengerjaan: 33 % Deni


28 Jul 2018 15:45:40

...

Pas.bt pondasi gorong2 plat beton sta 0 + 300an..bukan sta 1+000

Mahmud Hidayat


28 Jul 2018 11:34:34

...

Deni


28 Jul 2018 11:34:04

...

Penggalian gorong gorong STA 0+539

Deni


27 Jul 2018 10:50:45

...

Penggalian gorong" kedua

Deni


27 Jul 2018 10:49:54

...

STA +0.405 gorong"

Deni


27 Jul 2018 10:47:54

...

Deni


27 Jul 2018 10:47:33

...

STA +0.350

Deni


27 Jul 2018 10:46:41

...

Deni


27 Jul 2018 10:46:14

...

STA +0.300

Deni


27 Jul 2018 10:45:34

...

Deni


27 Jul 2018 10:45:11

...

STA +0.250

Deni


27 Jul 2018 10:44:33

...

Deni


27 Jul 2018 10:44:16

...

STA +0.200

Deni


27 Jul 2018 10:43:32

...

Deni


27 Jul 2018 10:43:09

...

STA +0.150

Deni


27 Jul 2018 10:42:25

...

Deni


27 Jul 2018 10:41:41

...

STA +0.100

Deni


27 Jul 2018 10:40:55

...

Deni


27 Jul 2018 10:40:33

...

STA +0.050

Deni


27 Jul 2018 10:39:49

...

Deni


27 Jul 2018 10:39:30

...

Deni


27 Jul 2018 10:39:05

...

STA +0.000

Deni


26 Jul 2018 12:06:09

...

Deni


26 Jul 2018 12:03:26

...

Pasang batu belah STA+0.350-STA +0.400

Deni


25 Jul 2018 14:15:29

...

Deni


25 Jul 2018 14:14:52

...

Galian pas batu

Deni


25 Jul 2018 14:13:50

...

Gorong2 STA 0+405

Deni


23 Jul 2018 14:50:07

...

Mulai finishing pas. Batu

Deni


21 Jul 2018 17:31:18

...

Galian gorong2 plat sta 0 + 600 an

Mahmud Hidayat


21 Jul 2018 16:20:09

...

Galian pondasi STA 0+300 - 0+350

Progress Pengerjaan: 26 % Deni


21 Jul 2018 15:58:34

...

Finishing talud sta 0+050

Progress Pengerjaan: 25 % CV. KARTIKA


21 Jul 2018 11:25:52

...

Galian STA 300 - 350

Deni


20 Jul 2018 13:55:00

...

STA 0+150

Deni


19 Jul 2018 13:03:48

...

Galian gorong2 STA 0+405

Deni


18 Jul 2018 13:41:04

...

Pekerjaan galian dan pas batu talud

Progress Pengerjaan: 20 % Deni


18 Jul 2018 13:37:49

...

Deni


PEMELIHARAAN JALAN TEJASARI - SELANEGARA

Kontraktor : CV. KARTIKA
Jangka Waktu Selesai : 120 Hari
Mulai Pengerjaan : 08 Jun 2018
Selesai Pengerjaan : 05 Oct 2018
Deskripsi Progress : Sudah PHO

Progress Pengerjaan

98 %